The 2026 reactor pipeline comprises about 80 reactors under construction and roughly 120 planned worldwide, while the operating fleet totals about 440 reactors and 400 GWe across 31 countries [S1].
The operating fleet supplied 2702 TWh in 2025, equivalent to about 9% of global electricity generation, and construction activity is concentrated in Asia [S1].
2026 Grid-Connection Count and Capacity Baseline
About 80 power reactors were under construction in 15 countries, covering both large light-water units and smaller reactor designs [S1]. The associated fleet-wide reference points are approximately 440 operating reactors, 400 GWe of combined operating capacity, and 2702 TWh of nuclear electricity generated during 2025 [S1].
These figures use net rather than gross capacity, so they should not be merged directly with the rounded 400 GWe and about 80-unit construction figures in [S1].
The World Nuclear Industry Status Report 2026 provides dedicated graphics for annual grid connections and closures, China compared with the world, the operating fleet through mid-2026, and construction starts and delays [S2]. Figure 4 is therefore the relevant reference for tracking annual grid connections, while Figure 5 separates China’s contribution from the global pattern [S2].
What Counts as a 2026 Grid Connection
A grid connection is the point at which a reactor unit begins supplying electricity to the electrical system, and the annual count must be distinguished from the broader construction pipeline [S2]. Figure 4 explicitly tracks “Nuclear Power Reactor Grid Connections and Closures in the World,” while Figure 6 tracks the world reactor fleet from 1954 through mid-2026 [S2].
The distinction changes the answer materially: about 80 units under construction does not mean 80 grid connections in 2026, and roughly 120 planned units do not represent committed 2026 energisation [S1]. Scheduled starts also include units with different design capacities, from the 125 MWe ACP100 to the 1720 MWe EPR, so both unit count and megawatts must be tracked [S1].
The World Nuclear Association lists three units with stated start years in 2026 in the excerpt: ACP100 at 125 MWe gross, CFR600 at 600 MWe gross, and FBR at 500 MWe gross [S1]. The three units shown in the excerpt have a combined gross capacity of 1,225 MWe, but the truncated table does not establish that they constitute a complete schedule list or a verified 2026 grid-connection total.
China Dominates the Construction Pipeline

Most reactors under construction or planned are in Asia, and the scheduled list supports that concentration [S1]. Two of the 2026 entries shown in the excerpt are in China: ACP100 at 125 MWe gross and CFR600 at 600 MWe gross [S1].
The 2026 report isolates China in Figure 5 for global grid connections and closures, Figure 8 for reactors under construction in China and worldwide, and Figures 13, 20, 21 and 22 for construction starts, fleet expansion, construction history and construction time [S2]. That presentation supports direct comparison of Chinese commissioning volume with the world total instead of relying on a single country’s project count.
The excerpt shows two units in China and one in India, but its truncation does not support a complete geographic breakdown of the 2026 schedule. India’s Kalpakkam PFBR, an FBR unit with a gross capacity of 500 MWe, is the only additional Indian entry shown in the excerpt [S1].
Large Units and SMRs Affect Capacity per Connection
Grid-connection count and added capacity are different metrics because unit size varies substantially [S1]. Among the three units shown for 2026, the ACP100 has the smallest gross capacity at 125 MWe and the CFR600 the largest at 600 MWe [S1].
The supplied schedule excerpt includes the 125 MWe ACP100 with a stated start year of 2026 [S1].
For procurement and grid planning, capacity should therefore be separated into unit count, gross nameplate megawatts, net electrical output and actual electricity delivered. Figures 6 and 7 provide the operating-fleet and under-construction context, while Figure 10 tracks average annual construction times and Figure 11 records delays for units commissioned during 2023–2025 [S2].
Grid Connections Must Be Reconciled With Closures

New grid connections do not produce an equivalent net increase when retired units leave service [S1]. Over the preceding 20 years, 101 reactors started operation while 111 were retired, illustrating how closures can offset additions even during a sustained construction program [S1].
Figure 4 pairs grid connections with closures, and Figure 18 covers the age distribution of closed nuclear power reactors, while Figure 19 addresses reactor closure age [S2]. These datasets support two separate measures: gross annual additions and net change in operating reactor count after permanent shutdowns.
Age and retirement schedules are not secondary to connection planning. The 2026 report includes an operating-fleet age distribution in Figure 15, age distributions for France and Japan in Figures 28 and 36, and separate closure-age data in Figure 19 [S2]. These references allow planned additions to be compared with units approaching retirement rather than treating all closures as interchangeable.
Schedule Risk Determines the 2026 Count
Announced start years are planning references, not guaranteed grid-connection dates, because construction delays can move a unit across reporting years [S2]. Figure 10 presents average annual construction times worldwide, Figure 11 covers delays for units commissioned during 2023–2025, and Figure 14 records cancelled or suspended reactor construction projects [S2].
The 2026 scheduled list spans 11 reactor model families, including ACP100, CFR600, FBR, VVER-1000, PHWR-700, VVER-TOI and APR1400 [S1]. A procurement forecast based only on the number of named projects would miss the distinction between a 125 MWe ACP100, a 600 MWe CFR600 and a 1400 MWe APR1400 [S1].
For equipment suppliers, the reliable sequence is to track construction starts, monitor delay factors, separate grid connections from commissioning milestones, and then reconcile additions against closures. For grid planners, the same sequence must be applied to net capacity and electricity output, not only to unit count [S1][S2].
The next trackable check is the annual unit and capacity total in Figure 4 of the World Nuclear Industry Status Report 2026, followed by the China comparison in Figure 5 and the closure balance for the same period [S2].