Gantry Crane

A gantry crane is a bridge crane that carries its own load path to the ground. Instead of hanging a bridge girder from runway beams built into a building, it supports that girder on two vertical legs that travel on rails or rubber tyres at ground level. Because it needs no surrounding structure, the gantry crane is the workhorse of open yards, quaysides, container terminals, shipyards, and any process that must straddle a fixed footprint such as a casting pit or a stockyard.

The family ranges from a one-tonne portable shop frame to a 2,000-tonne shipyard Goliath, and includes the rubber-tyred (RTG) and rail-mounted (RMG) container gantries that move most of the world's intermodal freight. This guide explains the types, the duty and structural standards that govern them, and the parameters that actually drive selection.

Large yellow double-girder gantry crane straddling a steel slab stockyard at the Avilés steelworks, its bridge girder carried on its own vertical legs at ground level

Photo: Borvan53, CC BY-SA 4.0, via Wikimedia Commons

This guide is written for procurement engineers and design engineers specifying lifting equipment. It covers 6 chapters from what a gantry crane is, through single and double girder types, RTG and RMG container cranes, duty classification, and span and wheel-load sizing, to the selection decision sequence, plus 7 selection FAQs. All parameters reference the public design standards CMAA Specification No. 70, FEM 1.001, ISO 4301, ASME B30.2, EN 13001, and DIN 536 crane rail.

Chapter 1 / 06

What is a Gantry Crane

A gantry crane is a type of bridge (or overhead travelling) crane in which the horizontal bridge girder is supported not by elevated runway beams fixed to a building, but by its own vertical support legs that travel on ground-level rails or on rubber tyres. The hoist trolley traverses across the bridge, the bridge travels along the runway, and the hoist raises and lowers the load, giving three orthogonal axes of motion over a rectangular working envelope. This self-supporting structure is the defining difference from an overhead bridge crane and is what allows a gantry to work in the open air, with no building required.

Structurally, a gantry crane has four functional assemblies: (1) the bridge girder, single or double, that spans between the legs and carries the trolley; (2) the support legs and the sill beams or end carriages at their feet, which transfer the entire load to the wheels; (3) the travel gear, namely the wheels, bogies, drives, and either rails or tyres that move the crane along the runway; and (4) the hoisting mechanism, normally a wire-rope or chain hoist trolley, plus the spreader, hook, or grab that engages the load. On large machines a driver cab, festoon or cable reel power feed, anemometer, and rail clamps complete the package.

The industrial history of the gantry runs in parallel with heavy industry itself. Portal and gantry frames were adapted for shipyards in the early twentieth century to lift hull sections that no jib crane could reach, and the term Goliath came to denote the largest shipbuilding gantries. The Samson and Goliath cranes at Belfast, built by the German firm Krupp and erected in 1969 and 1974, became landmarks of that era. The container revolution from the 1960s onward drove a second lineage: the ship-to-shore (STS) portainer at the quay, and the RTG and RMG stacking cranes in the yard, which together made modern intermodal shipping possible. Konecranes later built a shipyard Goliath for the Polo Naval do Rio Grande yard in Brazil with a 210 metre rail span and a 2,000 tonne lifting capacity, an indication of the scale this category now reaches.

In terms of working scale, gantry cranes span several orders of magnitude. A portable aluminium A-frame shop gantry lifts perhaps 250 kilograms to 5 tonnes and rolls on castors. A general industrial double-girder gantry lifts 5 to 100 tonnes across spans of 10 to 40 metres. Container gantries lift 30 to 65 tonnes under the spreader. At the top end, shipyard Goliaths exceed 1,000 tonnes. No single design covers this range: the essence of selection is matching the duty, span, load, and environment to the correct configuration and the correct design code.

Four engineering decisions dominate the lifecycle cost and safety of any gantry: the duty classification (how hard it works), the structural span and wheel load (what the civil works must carry), the hoisting and travel speeds (productivity), and the environmental design case (indoor, outdoor, wind, corrosion, explosion risk). The remaining chapters take these in turn.

Chapter 2 / 06

Gantry Crane Types

Gantry cranes are classified first by frame geometry and second by how they travel and what they handle. Frame geometry sets the headroom, the achievable lift height, and the capacity ceiling; the travel system sets where the crane can work and how it is powered. Choosing the wrong frame is the most common and most expensive specification error, because it cannot be corrected after the steel is built. The table below summarises the main families and their typical working envelopes.

TypeFrame / TravelTypical CapacityTypical SpanTypical Application
Portable / A-frameLight frame on castors0.25 to 5 t2 to 6 mWorkshop, garage, fixed-point lifts
Single girder gantryOne beam, underslung hoist2 to 20 t8 to 30 mLight industry, yards, storage
Double girder gantryTwo beams, top-running trolley10 to 100 t10 to 40 mHeavy industry, fabrication, casting
Semi-gantryOne leg + wall runway5 to 50 t10 to 30 mWorkshop bays with one strong wall
Goliath (shipyard)Heavy double girder, legs100 to 2,000 t100 to 210 mShipbuilding, hull block assembly
RTG (rubber-tyred)Rubber tyres, steerable30 to 65 t5 to 9 rows + laneContainer stacking yards
RMG (rail-mounted)Fixed rail, electricup to 65 t20 to 55 mAutomated yards, rail intermodal
STS (ship-to-shore)Quay rail, cantilever boom40 to 100 t40 to 70 m outreachQuayside vessel loading

Single girder gantries use one main beam with an underslung hoist trolley running on its lower flange. They are the lighter, cheaper, lower-headroom option and cover the bulk of general duty up to roughly 12.5 to 20 tonnes and spans up to about 25 to 30 metres. Double girder gantries run a top-mounted trolley on rails laid over two parallel girders, which lets the hook rise between the beams for maximum lift height and lets the bridge carry walkways, festoons, magnet or grab equipment, and far higher loads. The accepted rule of thumb is to step up to double girder above about 20 tonnes capacity, above about 25 metres of span, or whenever maximum hook height is the binding constraint.

Semi-gantries are hybrids: one side runs on a ground rail on a leg, the other on an elevated wall-mounted runway. They suit a building where one wall can carry a high rail but the floor on the other side cannot accept a second leg row, recovering floor space along that wall. Goliath cranes are simply very large double-girder gantries, used in shipyards to lift hull blocks of hundreds of tonnes and to assemble vessels outside the dry dock.

Container gantries form their own sub-family. A rubber-tyred gantry (RTG) rolls on tyres and is steerable, so it can move between yard blocks and works without any fixed rail; it typically spans five to nine container rows plus a truck lane, stacks one-over-three to one-over-six containers high, and lifts 30 to 65 tonnes under the spreader. A rail-mounted gantry (RMG) runs on fixed rails for precise, repeatable positioning that suits electric drive and automation; Kalmar RMGs, for instance, offer rail spans of 20 to 55 metres, capacities up to 65 tonnes, outreach up to 18 metres, and stacking up to one-over-six. The ship-to-shore (STS) crane is a quayside portal gantry with a long cantilever boom reaching over the vessel; Post-Panamax machines feature outreach of 40 to 70 metres, lift height above the rail of roughly 35 to 55 metres, and capacities of 40 to 100 tonnes.

Chapter 3 / 06

Duty Classification and Standards

Before any girder, leg, wheel, or hoist can be sized, the crane must be assigned a duty classification. Duty is the single most important input to a crane design, because it sets the fatigue stress range that the steel structure and the mechanisms must survive over the design life. Two parallel standard systems dominate: the North American CMAA and ASME framework, and the European FEM and ISO framework. The table below maps the two systems and their service intent.

CMAA ClassFEM / ISO GroupService IntentLoad Cycle Range
Class AM3 (~400 h)Standby / infrequentN1: 20k to 100k
Class BM3 to M4Light serviceN1: 20k to 100k
Class CM5 (~1,600 h)Moderate serviceN2: 100k to 500k
Class DM6 (~3,200 h)Heavy serviceN3: 500k to 2M
Class EM7 (~6,300 h)Severe serviceN4: over 2M
Class FM8Continuous severeN4: over 2M

CMAA Specification No. 70 covers top-running, double-girder bridge and gantry cranes, and its companion CMAA Specification No. 74 covers single-girder cranes. CMAA sorts cranes into six service classes from A to F. Class A is standby or infrequent service such as a powerhouse crane that lifts rarely and at slow speed. Class C is moderate, typical of general assembly and maintenance. Class D is heavy, typical of foundries and busy machine shops, and Class F is continuous severe service, handling loads near rated capacity throughout its life. The classes correspond to load-cycle ranges, where a load cycle is one complete hoist-and-lower of a load: N1 covers 20,000 to 100,000 cycles, N2 covers 100,000 to 500,000, N3 covers 500,000 to 2,000,000, and N4 covers more than 2,000,000 cycles.

FEM 1.001 (Rules for the Design of Hoisting Appliances) and the international standard ISO 4301 express the same engineering idea as mechanism groups M1 through M8. The group combines the total expected operating time with a load spectrum factor that weights how often the crane lifts near full load. For a representative load spectrum, M3 corresponds to roughly 400 hours of full-load equivalent use, M5 to about 1,600 hours, M6 to about 3,200 hours, and M7 to about 6,300 hours. M4 is the typical default for general industrial cranes, while M6 and M7 designate super-duty and ultra-duty machines that run heavy loads for many hours a day. The FEM and ISO groups are broadly equivalent to the CMAA classes, though the systems use different mathematics and should never be assumed numerically identical across a contract boundary.

Hoist duty is classified separately from crane (structure) duty. A crane carrying a CMAA Class D structure designation may still fail prematurely if the hoist is rated only to a light ISO M4 hoist group, because the hoist motor, gearbox, brake, and rope reeving wear on their own duty curve. In North American practice the hoist often carries an ASME HMI / H-class rating (H2, H3, H4) while the bridge and trolley follow CMAA, so both numbers must appear on the order.

Structural strength design is governed regionally by additional codes: ASME B30.2 (Overhead and Gantry Cranes) and OSHA 1910.179 in the United States, the harmonised European standard series EN 13001 (Cranes, General Design) referenced by FEM, the terminology and classification standards ISO 4306 and ISO 4301, and the Chinese national standard GB/T 14406 for general-purpose gantry cranes. The contract must name which code governs, because allowable stresses, impact factors, and test-load percentages differ between them.

Chapter 4 / 06

Span, Wheel Load and Rail

Three geometric quantities define how a gantry sits on the site: span, height, and the wheel load it transmits to the foundation. These are the numbers the civil and structural engineers need before any concrete is poured, and getting them wrong is far more expensive than getting the crane wrong, because foundations cannot be re-sized after casting.

Span is the centre-to-centre distance between the two running rails (or tyre paths), and it is set by the footprint the crane must straddle: a workshop bay width, the number of container rows in a stack, the gauge of a casting pit, or the clear width of a stockyard. Lift height (or hook height) is the vertical distance the hook can rise above the ground, fixed by the leg height and, for double-girder machines, by the headroom recovered between the girders. Outreach and back-reach matter only on cantilever cranes such as STS and cantilever RMG machines, where the boom or girder extends beyond the legs to reach over a vessel or a road or rail lane.

Wheel load is the most important civil interface. The maximum wheel load equals the crane dead weight plus the rated load plus the dynamic impact allowance, distributed across the wheels in one end carriage, and it commonly reaches several hundred kilonewtons even on mid-sized cranes. The civil engineer needs the maximum wheel load, the wheel spacing, the number of wheels per corner, and the buffer (end-stop) impact force to design the rail beam, the rail fixings, and the foundation. The rail profile is then chosen by head width to spread that wheel load without crushing or excessive wear. The DIN 536 crane rail series is the most widely specified worldwide; the table below lists the standard profiles.

DIN 536 ProfileHead WidthTotal HeightBase WidthMassTypical Use
A4545 mm55 mm125 mm22.1 kg/mLight cranes
A5555 mm65 mm150 mm31.8 kg/mLight to medium
A6565 mm75 mm175 mm43.1 kg/mMid-range industrial
A7575 mm85 mm200 mm56.2 kg/mMid to heavy
A100100 mm95 mm200 mm74.3 kg/mHeavy / port
A120120 mm105 mm220 mm100 kg/mHeavy port cranes

As a practical mapping, A45 and A55 suit light-duty cranes, A65 and A75 cover the bulk of mid-range industrial gantries, and A100 and A120 are reserved for heavy and port applications such as STS and RMG cranes. DIN 536 rails use a wide base, a low centre of gravity, and a thick web specifically to resist the high lateral wheel forces a crane imposes on cornering and skew. The rail must also be specified with its fixing system (welded sole plates, or clips with elastic pads) and, for outdoor cranes, with a defined rail-end gap allowance for thermal expansion.

Outdoor gantries add a further structural case: wind. The in-service wind is the limit under which operation may continue, commonly around 20 metres per second, beyond which the crane must stop. The out-of-service or storm wind is the survival case the parked crane must withstand, often in the range of 42 to 55 metres per second or higher depending on the regional code and the site exposure. When wind exceeds the in-service limit, the crane is parked and locked down with rail clamps that grip the running rail, plus storm anchors or stowage pins tying it to the foundation. Large port cranes add motorised storm pins and an anemometer interlock. The design wind region and exposure must be stated in the enquiry, because under-specifying it has historically caused cranes to be blown along or off their rails.

Chapter 5 / 06

Key Specification Parameters

A gantry crane data sheet may list dozens of figures, but a manageable set of parameters genuinely drives selection. Reading them correctly, and distinguishing rated capacity from working envelope and from duty, is the core skill of a lifting-equipment buyer. The parameters below should appear on every enquiry and every quotation.

Rated lifting capacity (SWL) is the maximum safe working load at the hook or under the spreader, stated in tonnes. For container cranes it is quoted under the spreader, so the spreader's own weight is already deducted. Capacity must be matched to the heaviest actual lift plus a margin, never to the average lift. Span, as defined in Chapter 4, sets the footprint. Lift height and, for cantilever cranes, outreach and back-reach define the reachable envelope.

Operating speeds determine productivity and are quoted for the three motions, often with a fast and a creep (micro-speed) value. Representative industrial figures are a main-hoist speed of roughly 5 metres per minute with a 0.83 metre per minute creep, a trolley traverse of about 20 metres per minute, and a bridge (gantry) travel of about 32 metres per minute. Container cranes run far faster: RTG hoisting of 12 to 46 metres per minute and gantry travel of 45 to 90 metres per minute, and STS cranes hoisting of 60 to 180 metres per minute with trolley speeds up to 150 to 240 metres per minute. Higher speeds raise throughput but also raise dynamic loads, drive ratings, and cost.

Duty classification (CMAA class and FEM or ISO group for both crane and hoist) sets the design life and must be matched to real usage, as Chapter 3 explains. Maximum wheel load, wheel spacing, and number of wheels are the civil interface. Power supply and feed method covers supply voltage and frequency, plus how power reaches the moving crane: festoon trolley line, cable reel, conductor bar, or, for RTG cranes, an onboard diesel-electric or hybrid power pack. The electrical specification below summarises the controls and protection envelope:

  • Drive type: variable-frequency drives (VFD) are now standard on all three motions, giving soft start, anti-sway, and accurate spotting; pole-change or resistor control survives only on the lightest cranes.
  • Ingress protection: panel and motor enclosures rated IP54 indoors, IP55 to IP66 outdoors, with anti-condensation heaters for humid or coastal sites.
  • Limit and safety devices: hoist upper and lower limits, travel end limits, overload protection (load cell or torque limiter), and anti-collision sensors on multi-crane runways.
  • Anti-sway and positioning: electronic sway control and laser or encoder positioning on automated RMG and STS cranes.
  • Environment options: explosion-proof (ATEX / IECEx) execution for hazardous areas, and corrosion protection grade (paint system class to ISO 12944) for coastal or chemical sites.

Test load and commissioning requirements close the specification. New cranes are typically proof-load tested at 110 to 125 percent of rated capacity under the governing code, and the certified test report, together with the duty class and the design code, forms the legal basis for safe operation. Always confirm whether the quoted price includes erection, commissioning, the first statutory examination, and the rail and runway, because on large gantries these can rival the cost of the crane itself.

Chapter 6 / 06

Selection Decision Factors

To translate the previous chapters into a specific machine, work through the decision sequence below in order. Most gantry-crane mistakes come not from a single wrong number but from deciding a downstream parameter (such as the hoist) before an upstream one (such as the duty class) is fixed. These steps double as a fixed RFQ template.

  1. Load, span and height: Establish the heaviest actual lift (plus margin) for the rated capacity, the footprint to straddle for the span, and the required hook height. These three numbers fix the frame size and, with the rule of thumb above 20 tonnes or 25 metres, the choice between single and double girder.
  2. Frame and travel type: Choose full gantry, semi-gantry, portable, or a container type (RTG, RMG, STS) from Chapter 2, and decide rail-mounted versus rubber-tyred travel. Rails give precision and electric drive; tyres give layout flexibility.
  3. Duty classification: Assign the CMAA class and the FEM or ISO group for both the structure and the hoist, based on real cycles per hour and hours per day, not on a guessed nameplate. Each duty step up adds steel, hoist rating, and cost.
  4. Civil interface: Calculate and hand over the maximum wheel load, wheel spacing, number of wheels, and buffer impact force, then select the DIN 536 rail profile and rail fixing per Chapter 4. Confirm the foundation can carry it before ordering.
  5. Speeds and drives: Set hoist, trolley, and travel speeds, including creep speeds, and specify VFD control with anti-sway where spotting accuracy or throughput matters.
  6. Environment: Indoor or outdoor, design wind region (in-service and storm), temperature range, corrosion grade (ISO 12944 paint class), and any explosion-proof (ATEX / IECEx) requirement. Outdoor cranes must include rail clamps and storm anchors.
  7. Power and controls: Supply voltage and frequency, power-feed method (festoon, cable reel, conductor bar, or onboard power pack), control mode (cab, pendant, radio remote, or automated), and the limit, overload, and anti-collision safety devices.
  8. Code, test and documentation: Name the governing design code (CMAA 70, FEM 1.001, EN 13001, ASME B30.2, or GB/T 14406), the proof-test percentage, and the required certificates, then confirm scope: erection, commissioning, first statutory examination, rail, and runway.

One dimension that buyers regularly overlook is serviceability: local spare-parts inventory, field service and re-rope or re-wheel capability, availability of structural inspection and fatigue assessment over a 20 to 40 year design life, and remote-monitoring or condition-monitoring support. A gantry crane is a multi-decade asset, and the manufacturer's service network often matters more over its life than the purchase price. For industrial and process gantries, established builders include Konecranes (CXT and SMARTON hoists on gantry frames), Demag (DH and DR rope hoists), Street Crane (ZX hoist and full-portal Goliath cranes), ABUS, and SWF Krantechnik. For port container cranes the major STS, RTG, and RMG builders are Konecranes, Kalmar (Cargotec), Liebherr, and ZPMC, while suppliers such as Weihua, Henan Mine, and Nucleon offer CMAA and FEM rated double-girder gantries for general industry at lower cost. Whichever supplier you shortlist, confirm the duty class, the governing code, and the local service coverage first.

FAQ

What is the difference between a gantry crane and an overhead bridge crane?

An overhead bridge crane carries its bridge girder on elevated runway beams supported by the building structure or columns, so the load path runs into the building frame. A gantry crane carries the same bridge girder on its own vertical legs that run on ground-level rails or rubber tyres, so it needs no supporting building at all. This makes gantry cranes the default for open yards, quaysides, container terminals, and shipyards where there is no roof structure to hang a runway from. A semi-gantry is a hybrid: one side runs on a ground rail on legs, the other on an elevated wall-mounted runway, which suits buildings where one wall can carry the rail but the floor cannot accept a second leg row.

When should I choose a single girder versus a double girder gantry?

Single girder gantries use an underslung hoist trolley running on the bottom flange of one main beam. They are lighter, cheaper, and lower in headroom loss, and they cover most duties up to roughly 12.5 to 20 tonnes with spans up to about 25 to 30 metres. Double girder gantries run a top-mounted trolley on rails laid over two parallel beams. They are mandatory once you need high hook height (the hook can rise between the girders), capacities above about 20 tonnes, long spans, or auxiliary equipment such as a maintenance walkway, festoon, or magnet cable reel mounted on the bridge. As a rule of thumb, choose double girder above 20 tonnes or 25 metres of span, or whenever maximum lift height matters.

What do CMAA Class A to F and FEM duty groups actually mean?

CMAA Specification No. 70 sorts cranes into service classes A through F by how hard they work. Class A is standby or infrequent service, Class C is moderate (typical maintenance and assembly), Class D is heavy, and Class F is continuous severe service near rated capacity. The classes map to load-cycle ranges: N1 is 20,000 to 100,000 cycles, N2 is 100,000 to 500,000, N3 is 500,000 to 2,000,000, and N4 is over 2,000,000 cycles. The European FEM 1.001 and ISO 4301 systems express the same idea as mechanism groups M3 through M8, where M3 corresponds to roughly 400 hours of full-load use, M5 to 1,600 hours, M6 to 3,200 hours, and M7 to 6,300 hours. You must classify duty before sizing any structural member, because the duty group sets the fatigue stress range the steel and the hoist must survive.

How do I size the span and wheel load for a gantry crane?

Span is the centre-to-centre distance between the two running rails and is fixed by the footprint you must straddle: a workshop bay, a container stack, or a casting pit. Wheel load is the critical civil interface because it drives the rail profile and the foundation. Maximum wheel load equals the dead weight of the crane plus the rated load and impact, distributed across the end-truck wheels, and it can reach hundreds of kilonewtons even on modest cranes. The rail profile is then selected by head width: DIN 536 A45 (45 mm head, 22.1 kg/m) and A55 (55 mm, 31.8 kg/m) suit light cranes, A65 (65 mm, 43.1 kg/m) and A75 (75 mm, 56.2 kg/m) mid-range industrial cranes, and A100 (100 mm, 74.3 kg/m) and A120 (120 mm, 100 kg/m) port and heavy cranes. Always give the civil engineer the maximum wheel load, wheel spacing, and number of wheels per corner before pouring foundations.

What is the difference between an RTG and an RMG container crane?

Both stack containers in a yard, but they differ in how they move and how flexible the layout is. A rubber-tyred gantry (RTG) rolls on rubber tyres and can be steered between blocks, so it moves freely around the terminal and needs no fixed rail, at the cost of a diesel or hybrid power pack and lower automation. An RTG typically spans five to nine container rows plus a truck lane, stacks one-over-three to one-over-six high, and lifts 30 to 65 tonnes under the spreader. A rail-mounted gantry (RMG) runs on fixed rails, which gives precise, repeatable positioning ideal for automation and electric drive, but locks the crane to one block. Kalmar RMGs, for example, offer rail spans of 20 to 55 metres, lift up to 65 tonnes, reach an outreach up to 18 metres, and stack up to one-over-six. RMGs dominate automated stacking yards and rail intermodal terminals; RTGs dominate flexible manually operated yards.

What wind speed must a gantry crane survive, and how is it secured?

Outdoor gantry cranes are designed for two wind conditions. The in-service wind is the maximum wind under which the crane may keep working, commonly around 20 metres per second, above which operation must stop. The out-of-service (storm) wind is the survival case the parked, unloaded crane must withstand, often 42 to 55 metres per second or higher depending on the regional design code. Above in-service wind, the crane is parked and secured by rail clamps that grip the running rail, plus storm anchors or stowage pins that tie the crane to fixed foundation points. Large port cranes add motorised storm pins and anemometer interlocks that automatically warn or stop the crane. Skipping wind design is a recorded cause of cranes blowing off their rails, so the design wind region must be stated in the order.

Which manufacturers and series should I shortlist for gantry cranes?

For industrial and process gantries, Konecranes (CXT and SMARTON hoists on gantry frames), Demag (DH and DR rope hoists), Street Crane (ZX hoist, full-portal Goliath cranes), ABUS, and SWF Krantechnik cover light to heavy duty. For shipyard Goliath cranes up to 1,000-plus tonnes, Konecranes is the reference; its Polo Naval do Rio Grande crane held a 210 metre rail span and 2,000 tonne capacity. For port container cranes, Konecranes, Kalmar (Cargotec), Liebherr (LCC), and ZPMC are the major STS, RTG, and RMG builders. Chinese suppliers such as Weihua, Henan Mine, and Nucleon supply CMAA and FEM rated double-girder gantries at lower cost for general industry. Always confirm the duty class, applicable design code (CMAA 70, FEM 1.001, EN 13001, or GB/T 14406), and local spare-parts and service coverage before shortlisting.

Ask SpecForge AI