2026 LNG Liquefaction Additions: 37 MTPA Capacity Wave

Table of Contents
  1. 37 MTPA of scheduled 2026 liquefaction capacity
  2. North America supplies the largest regional expansion
  3. Project pipeline by country and scale
  4. Capacity choices: brownfield expansion, new trains and floating LNG
  5. Feedgas, pipelines and commissioning constrain output
  6. Supply growth must be measured against demand
2026 LNG Liquefaction Additions: 37 MTPA Capacity Wave

Approximately 37 MTPA of new LNG liquefaction capacity was slated to enter service in 2026, after 51 MTPA entered service in 2025 [S6].

The additions form part of a larger expansion wave: A total of 68.4 Mtpa of liquefaction capacity reached final investment decision during 2025 [S4].

37 MTPA of scheduled 2026 liquefaction capacity

The 2026 schedule comprises approximately 37 MTPA of new liquefaction capacity [S6].

Capacity additions must be distinguished from actual production. A terminal can have nameplate liquefaction capacity before achieving full commercial operation, while startup performance depends on commissioning, feedgas quality, train reliability, and supply-chain readiness. EIA project schedules distinguish baseload capacity and estimated online dates from the later ramp to full production [S2].

The broader development pipeline remained larger than the 37 MTPA scheduled for 2026.

North America supplies the largest regional expansion

North American LNG export capacity was projected to rise from 11.4 Bcf/d at the beginning of 2024 to 28.7 Bcf/d in 2029 if projects under construction operate as planned [S2]. The increase of 17.3 Bcf/d includes an estimated 13.9 Bcf/d of additional U.S. liquefaction capacity between 2025 and 2029, 2.5 Bcf/d in Canada, and 0.6 Bcf/d in Mexico [S2].

Exporters in Canada announced plans to add 2.5 Bcf/d of LNG export capacity over 2025–2029 [S2].

Project pipeline by country and scale

These figures describe development pipelines rather than guaranteed 2026 commissioning.

Canada and Mauritania/Senegal joined the ranks of LNG-exporting nations for the first time [S4].

Capacity choices: brownfield expansion, new trains and floating LNG

The capacity comparison is not limited to a single project format. Fixed North American trains provide large baseload volumes, including 1.6–2.2 Bcf/d for the five U.S. projects listed by EIA [S2]. Canada’s LNG Canada uses two 0.9 Bcf/d trains, while its proposed second phase would add two trains and take total capacity to 3.68 Bcf/d [S2].

Floating LNG offers a different development profile. Exporters in Mexico announced plans to add 0.6 Bcf/d of LNG export capacity over 2025–2029 [S2].

On decision criteria, fixed trains provide larger individual baseload blocks, while floating LNG can offer modular deployment. Schedule certainty remains a separate variable: the 37 MTPA figure for 2026 is a stated startup schedule, whereas the 68.4 Mtpa development figure covers capacity that reached final investment decision during 2025 [S4][S6].

Feedgas, pipelines and commissioning constrain output

New liquefaction capacity does not eliminate upstream and midstream constraints. EIA identified pipeline construction delays as a supply risk for U.S. Gulf Coast terminals because feedgas must reach plants from production areas [S2]. Projects also face construction, financing, labor, equipment and commissioning risks before reaching nameplate production.

Operational history illustrates the gap between capacity additions and reliable output. Global LNG trade growth in 2025 was driven by expanding supplies from the United States, Qatar, and other producers, while Canada and Mauritania/Senegal joined the ranks of LNG-exporting nations for the first time [S4]. Global LNG trade reached 437 million tonnes in 2025, a 6.3% increase and the strongest growth since 2022 [S4].

This demand expansion supports the business case for new capacity, but trade volume does not guarantee utilization because liquefaction plants serve contracted and spot cargoes across multiple markets [S4].

Supply growth must be measured against demand

A 2026–2035 outlook sets global LNG demand at approximately 297 MTPA by 2030 against supply capacity of about 575 MTPA, implying a potential structural surplus of roughly 278 MTPA [S8]. The scenario is a market balance estimate, not a forecast that all 575 MTPA will operate at full utilization.

Supply and utilization should therefore be tracked separately. The most measurable 2026 signals are actual commissioning of the 37 MTPA scheduled wave, sustained commercial operation of Plaquemines LNG phases and Corpus Christi Stage III, and the contribution from LNG Canada as its two trains move toward full capacity [S2][S6].

Additional 2026 indicators include monthly US export volumes against the 110.7 million tonnes exported in 2025, commissioning progress at the five listed US projects, and realized contract coverage for new cargoes [S2][S4].

Frequently asked questions

How much new LNG liquefaction capacity was scheduled to enter service in 2026?

Approximately 37 MTPA of new LNG liquefaction capacity was slated to enter service in 2026, following 51 MTPA added in 2025. The 2026 wave equals about 7% of the 524.5 Mtpa global liquefaction capacity recorded at the end of 2025.

Does 37 MTPA of scheduled 2026 LNG capacity equal expected production?

No. The 37 MTPA figure represents scheduled capacity additions, not guaranteed output, because commissioning, feedgas quality, train reliability, and supply-chain readiness affect startup performance. Project schedules distinguish nameplate baseload capacity and estimated online dates from the later ramp to full production.

Which fixed U.S. LNG projects were under construction with final investment decision, and what capacity do they add?

The five listed U.S. projects were Port Arthur LNG Phase 1 at 1.6 Bcf/d, Rio Grande LNG at 2.1 Bcf/d, Woodside Louisiana LNG at 2.2 Bcf/d, Golden Pass LNG at 2.1 Bcf/d, and CP2 Phase 1 at 2.0 Bcf/d. Their combined nameplate liquefaction capacity was 10.0 Bcf/d.

How do fixed-train and floating LNG capacity options compare for 2026–2029 development?

Fixed North American trains provide individual baseload blocks of 1.6–2.2 Bcf/d, while floating LNG offers a more modular profile; Cedar LNG is sized at up to 0.4 Bcf/d and was expected to begin exports in 2028. Schedule certainty should be assessed separately because fixed projects may have larger volumes but different construction and commissioning timelines.

10 sources
  1. Global LNG Outlook 2024-2028
  2. North America's LNG export capacity could more than ... (Oct 16, 2025)
  3. Global LNG Capacity Tracker (Oct 1, 2026)
  4. World LNG Report 2026 (Jul 7, 2026)
  5. Liquefaction Capacity by Country Forecast to 2032 - Incorrys
  6. Natural gas and LNG: Top 5 market drivers for 2026 (Jan 14, 2026)
  7. US gas demand growth from LNG exports and data centers ... (Dec 17, 2025)
  8. Global LNG Outlook 2026-2035
  9. The LNG Wave in 2026/2027: Where will it go? (Feb 1, 2026)
  10. PRESS RELEASE

Need to source matching manufacturers or get a quote?

SpecForge connects industrial buyers with verified manufacturers. Submit your requirement and we will route it to matched suppliers.

Submit RFQ now →
Ask SpecForge AI