OEE, OOE and TEEP use the same productive-time numerator but divide it by different time bases: planned production time, staffed operating time, and all calendar time.
Report OEE for floor improvement, OOE for shift and labor planning, and TEEP for hidden-capacity and capital-investment analysis, with each metric defined before it enters a dashboard.
Metric Definitions and Time Denominators
OEE is Overall Equipment Effectiveness: the ratio of fully productive time to planned production time. Its three factors are Availability, Performance and Quality, and it exposes breakdowns, speed losses, minor stops and rejected output during scheduled production [S1][S3].
OOE is Overall Operations Effectiveness: the ratio of fully productive time to operating time, including breaks, meetings, scheduled maintenance and other planned stops inside the staffed shift [S1][S2]. This wider denominator exposes organizational loss that OEE can exclude when the time was already removed from the production schedule.
TEEP is Total Effective Equipment Performance: the ratio of fully productive time to all available time, normally 24 hours per day and 365 days per year, although a week can be used as a 168-hour period [S1][S2]. It combines OEE losses with schedule or loading loss.
The common calculation is Performance multiplied by Quality multiplied by Availability, but Availability changes with the time base. OEE uses Actual Production Time divided by Planned Production Time; OOE uses Actual Production Time divided by Operating Time; and TEEP uses Actual Production Time divided by All Time [S2].
Worked Comparison with One Asset
For one machine over one week, calendar time is 168 hours, operating time is 80 hours, planned production time is 66 hours, and unplanned stops total 8 hours. With 58 run hours, 90% Performance and 97% Quality, fully productive time is 58 multiplied by 0.90 multiplied by 0.97, or 50.6 hours [S4].
The resulting scores are 76.7% OEE, calculated as 50.6 divided by 66; 63.3% OOE, calculated as 50.6 divided by 80; and 30.1% TEEP, calculated as 50.6 divided by 168 [S4]. These are different answers to different questions, not competing estimates of the same result.
A second published example uses 65% OEE, 80 planned hours and 168 calendar hours. Utilization is 47.62%, so TEEP equals 0.6500 multiplied by 0.4762, or 30.95% [S3]. The same calculation is often written as TEEP equals OEE multiplied by Loading, where Loading is Planned Production Time divided by Calendar Time [S4].
By decision criterion, OEE is strongest for shift-level loss control, OOE for evaluating planned stops against staffed hours, and TEEP for estimating unused calendar capacity. A 76.7% OEE with 30.1% TEEP means efficient execution during planned production can still coexist with substantial unused calendar time.
Where Each Metric Belongs

OEE measures how effectively a manufacturing process or specific equipment performs during planned production time and is used for daily operational improvement. It is the appropriate daily metric for breakdowns, changeovers, micro-stops, reduced speed, startup rejects and production rejects [S1][S4]. Its denominator isolates losses that the shift team can influence while production was intended to run.
OOE measures equipment effectiveness over the plant's operating time, including staffed but idle time. It retains breaks, meetings, planned maintenance and inspection time in the denominator, making it suitable for questions about shift patterns, break scheduling, staffing coverage and planned maintenance policy [S2][S4].
TEEP is used for capacity and investment decisions. A high OEE combined with low TEEP indicates efficient equipment operated only during a limited schedule, leaving potential on nights or weekends. A low TEEP can therefore support adding a shift or extending operating hours before buying another machine [S3][S5].
OOE and TEEP are not substitutes for shop-floor accountability. OOE can show that planned stops consume staffed capacity, while TEEP can show that an asset sits idle outside the schedule. OEE remains the tighter diagnostic metric for reducing losses during production.
Application Suitability and Boundaries
OEE is not the right standalone metric for proving that a plant uses its assets around the clock. Its planned-production denominator can hide unused nights and weekends, producing a respectable score even when calendar utilization is weak [S3][S5].
OOE is not the right primary metric for capacity against a 24-hour calendar because it still excludes closed and unattended periods. It is also less suitable for daily loss elimination when the goal is specifically to diagnose breakdown, speed and quality losses during scheduled production [S1][S4].
TEEP is not a daily operating KPI and should not be used to blame a shift for time outside its operating plan. Its denominator includes schedule loss, maintenance windows, supply constraints and other excluded periods; these must be defined consistently before comparisons are made [S2][S3].
Each metric needs a fixed ownership boundary, especially for multi-station or product families. Changing planned stops, opening hours or calendar scope alters the denominator and can shift the reported result without any equivalent change in productive output.
Reporting Rules and Governance

Maintain one controlled definition for fully productive time, then publish the denominator beside every score. For example: 50.6 hours fully productive time divided by 66 planned hours equals 76.7% OEE; dividing the same numerator by 80 operating hours equals 63.3% OOE; dividing it by 168 calendar hours equals 30.1% TEEP [S4].
Classify changeovers carefully. One plant can count changeovers as planned and report higher OEE without being more effective, while OOE exposes time inside the operating window [S4]. Record planned maintenance, breaks, meetings, supply shortages and breakdowns separately rather than hiding them inside one availability value.
Use a two-layer report for most plants: OEE as the daily action metric and TEEP as the monthly or quarterly capacity metric. Add OOE when staffed-time policy, planned maintenance or labor utilization is under review. This keeps a tactical loss measure separate from a strategic capacity measure without maintaining three incompatible scorecards.
Set targets against the metric's actual purpose. A 100% TEEP would mean good output at maximum rate with no equipment losses and no schedule loss across all calendar time [S3]. That is a theoretical ceiling, not a normal operating target.
Choosing the Metric for the Decision
The direct decision is straightforward: choose OEE when the question is how well the asset performed during planned production, OOE when the question is how well the staffed operation used its open hours, and TEEP when the question is how much of the total calendar capacity is productive [S1][S4].
For a plant running two 8-hour shifts across five days, the calendar denominator is 168 hours, the operating denominator is 80 hours, and the planned-production denominator excludes defined breaks, meetings and maintenance [S2][S4]. Reporting all three without their denominators invites false comparisons between assets, lines and sites with different schedules.
Track the productive output numerator and the denominator separately. If output rises while OEE rises but TEEP falls, the asset is performing better during scheduled hours but gaining less of the available calendar. If OEE falls while OOE stays stable, inspect whether planned stops are masking worsening execution during production.
Use OEE for daily floor decisions, OOE for operational-policy decisions and TEEP for hidden-capacity and capital decisions. Publish the time basis with every percentage, preserve one definition of productive time, and escalate a metric only when the associated losses fall within the decision maker's control.