Electrodeionization

Electrodeionization, EDI or CEDI for the continuous form, removes residual ions from reverse osmosis permeate and similar feeds by combining ion exchange membranes, mixed bed ion exchange resin, and a direct current field in one module, producing ultrapure water continuously without the acid and caustic regeneration chemical trade a conventional mixed bed polisher carries. Feed flows through resin filled diluting chambers between anion and cation membranes, the DC field drives ions out of those chambers through the membranes into concentrating compartments that carry them to drain, the resin keeps the dilute chamber conductive at the ultrapure end, and water splitting at the bed interfaces regenerates the resin in place, in normal polarity or by periodic reversal, so the module polishes for years rather than exhausting by the shift. Properly fed EDI on good RO permeate delivers 10 to 18 megohm centimeter product, 0.055 to 0.1 microsiemens per centimeter, with silica polished to low parts per billion, at 80 to 95 percent recovery depending on hardness and CO2 management.

Procurement engineers meet these modules as the polish stage of ultrapure water trains in power generation, microelectronics, pharmaceutical and bioprocess, and general industry, and as the chemical free replacement for service degasifiers and mixed bed bottles where handling regeneration or renting exchange resin no longer suits the site. The decision this page settles is which module architecture and train arrangement fit the feed and the purity target: plate and frame against spiral wound EDI, the feed quality gates that decide whether EDI will run here at all, hardness, carbon dioxide, oxidants and temperature, the DC power and polarity reversal scope, and the recovery and cleaning basis. The answer lands as an RFQ line set, feed and product specification, module count and arrangement, electrical and recovery basis, and every chapter below feeds that line set so the EDI delivers megohms on this plant's water rather than on the datasheet's.

Membrane filtration element held out of its housing, the membrane separation hardware class of the purification train whose electrodeionization modules and stacks polish RO permeate to ultrapure water

Photo: Agne27, CC BY-SA 3.0, via Wikimedia Commons

This page treats electrodeionization as a purchasing object: how membranes, resin, and a DC field remove ions without regeneration chemicals, what feed quality gates decide whether a plant's water can run EDI, how plate and frame and spiral wound modules divide the market, what product and recovery numbers to guarantee, and how the whole decision folds into a defensible RFQ inside the ultrapure water train. It is written for engineers who specify water treatment equipment, not for readers who want a brochure summary.

Chapter 1 / 06

What an EDI Module Is and What Is Being Decided

The defining act of the machine is ion removal by the union of three physics that each industry knows alone. Ion exchange membranes pass only their counter ions, the electrodialysis tradition; mixed bed resin exchanges ions from the water onto its sites, the demineralizer tradition; and a DC field across the stack provides the driving force, pulling cations toward the cathode and anions toward the anode through the membrane pairs that bound each dilute chamber. Alone the resin would exhaust and need chemicals, alone the membranes would stall as the dilute stream went pure and nonconductive, and alone the field would just polarize the water. Together, the resin conducts the ions to the membranes at feed concentrations where water alone cannot, and the field's water splitting at the resin interfaces regenerates the sites continuously, so the module runs between cleanings and delivers its product without an acid or caustic molecule arriving at the plant.

What is being decided in this purchase is four commitments at once. First the feed basis: EDI is a polish stage, its feed must be RO permeate or equivalent, with the hardness, carbon dioxide, chlorine and oxidants, silica, and temperature gates the chapter 4 table quantifies, because the module's life is spent or saved upstream. Second the product specification: resistivity or conductivity target, silica, sodium, and any TOC expectation, with the module count and arrangement that deliver it at design flow. Third the mechanical and electrical scope: plate and frame stacks or spiral wound modules, the DC rectifier with its control, piping and valving for concentrate recirculation and electrode streams, and the recovery basis against the concentrate and electrode drain. Fourth the lifecycle basis: cleaning regime and chemicals, membrane and module replacement interval, and the instrumentation, resistivity and flow and pressure, that proves the train online. A buyer who leaves the feed gates unverified buys megohms that arrive degraded and blame upstream.

Against its neighbors EDI occupies precise ground in the ultrapure water train, the train the upw-system page maps as a whole and deliberately does not detail here. Reverse osmosis, the RO stage ahead of EDI, does the bulk removal and its membrane elements are bought on the purification pages of that family. Conventional mixed bed polishers, the exchange bottles and packed beds with chemical or service regeneration, are the incumbent EDI replaces on chemical handling and continuity grounds, and the upw-system page describes them as its own polish tradition. Electrodeionization is the module and stack stage itself, this page's authority, sitting after RO and optional degasification and before final filtration, ultraviolet sterilization, and distribution polishing. Analytical instruments, the conductivity meter, silica analyzer, sodium analyzer, and TOC analyzer, police both the feed gates and the product online. Naming the position keeps vendors quoting the stage, not the whole train or a fragment of it.

Standards frame the datasheet from the water side. Product water targets quote ASTM D1193 type I water practice and the pharmacopoeia purified water traditions where those apply, with resistivity at 25 deg C the headline number. Materials and construction follow the potable and pure water contact traditions, and sanitization expectations on pharma and bioprocess duty, hot water or chemical sanitize capability, are module architecture questions answered in the catalog section. Performance is vendor guaranteed territory, product resistivity and silica at stated feed and flow with the feed basis explicit, and the serious quotations arrive with feed requirements their guarantees assume. A datasheet that quotes megohms with no feed specification is a price tag, not a specification.

The station around the modules deserves naming in the RFQ too. Ahead of EDI, the RO train sets the feed with its own instrumentation, and a degasser, membrane or chemical, cuts carbon dioxide when the feed basis demands it, because CO2 loads the anion side of the stack and spends recovery. Between stages, cartridge filtration, the precision filter tradition, catches resin fines and particles that would foul the stack. The DC rectifier supplies the stacks with its control and interlocks, at amperage the module count sets. Downstream, ultraviolet sterilization and final filtration polish the product to the point of use, the distribution loop's instruments prove it continuously, and the reject and electrode streams route to drain or recycle per the water balance. Buying modules without the rectifier and recovery basis is how megohm disputes start.

Chapter 2 / 06

How Membranes, Resin, and the DC Field Work Together

Follow one ion through the stack. A sodium ion in the dilute chamber exchanges onto the cation resin, the field pulls it through the resin bed by electromigration, and the cation exchange membrane bounding the chamber on the concentrate side passes it into the concentrate stream while blocking anions trying to come back; chloride mirrors the journey through anion resin and the anion membrane on the other wall. The concentrate stream, a fraction of the feed recirculated in many designs, sweeps the ions to drain, and electrode compartments at the stack ends carry the electrode reactions and their gases to a separate drain. The stack is a battery of such chamber pairs under compression, dozens to hundreds depending on architecture, all driven by the one DC field the rectifier supplies.

Water splitting is the trick that makes it continuous. At the resin membrane interfaces in the dilute chamber, where the local solution has been depleted toward ultrapurity and the field concentrates, water dissociates into hydrogen and hydroxide ions, and these regenerate the resin sites in place, hydrogen ions replacing the cations on cation sites and hydroxide regenerating anion sites, exactly the chemistry a chemical regenerant would deliver, produced electrically and locally. This is why EDI never exhausts like a bottle, and also why the module's electrical operating point, current density against flow and feed, is a design quantity: too little field and regeneration lags leakage, too much and the energy burns in water splitting beyond the polish duty.

The feed gates exist because the same physics punishes shortcuts. Hardness, calcium and magnesium, concentrates in the concentrate chambers and on the membrane faces, scaling the stack the way it scales any surface, so feed hardness is held to parts per billion equivalent, commonly under 0.5 to 1 ppm as CaCO3 by vendor, which a properly softened or two pass RO feed delivers. Free chlorine and other oxidants attack the membranes and resin, held to under roughly 0.02 to 0.05 ppm, which a dechlorination stage upstream provides. Carbon dioxide passes the anion side as load, wasting capacity and recovery, so feeds high in CO2, after a single pass RO on alkaline water, take a degasser. Temperature sets conductivity and membrane behavior, quoted bands commonly 5 to 45 deg C, and iron and manganese foul the resin, held to the low parts per billion. The chapter 4 table gathers the numbers a specification meeting argues from.

Product quality lands on two numbers the train buys. Resistivity, the inverse of conductivity, is the headline: 10 to 18 megohm centimeter at 25 deg C is the healthy module band on compliant feed, the low microsiemens and below, with 18.2 megohm the theoretical pure water ceiling the best trains brush at the point of use with polishing beyond EDI. Silica is the second, reactive to the anion side performance and the number the power and microelectronics buyers watch, polished from tens of ppb feed to single digit and lower ppb product by module. Sodium, chloride, and TOC expectations follow by industry, TOC less an EDI duty than a whole train property, since the modules neither make nor remove much carbon. The guarantees quote these at stated feed, flow, and temperature, and the acceptance test holds the vendor and the plant to the same water.

Recovery and energy close the physics the purchase pays for. Module trains recover 80 to 95 percent of feed to product, the balance split between concentrate, which may recirculate to the RO feed in water tight plants, and the electrode stream, small and fixed by the stack design. Energy is modest, the DC field on the order of tens of kilowatt hours per thousand cubic meters of product by module design and feed, small against the RO stage's pumping power, and the rectifier's control basis, constant current or voltage, with the polarity reversal or reversal free architectures described next, decides how the train behaves through feed drift. The honest bid quotes energy and recovery at the plant's actual feed, not at a datasheet water nobody runs.

Chapter 3 / 06

Module Architectures and Duty Boundaries

Plate and frame stacks are the classic CEDI architecture: alternating dilute and concentrate compartments built from membranes, spacers, and electrodes, the dilute chambers filled with mixed resin, the whole bolted under compression between end plates, with feed, product, concentrate, and electrode ports manifolded. The architecture runs at high product purity, tolerates substantial flow per stack, and dominates the larger industrial and power trains, with module sizes from a few cubic meters per hour to tens per stack and stacks paralleled to the train capacity. Maintenance is at the stack level, gaskets and membranes inspected at rebuild, and the compression hardware and manifolds are site plumbing of ordinary skill.

Spiral wound EDI modules wrap the same physics around a center axis: membrane pairs and spacers wound spirally with the resin in the dilute chambers, the assembly in a pressure vessel shell like a membrane element. The architecture packages small and mid flows economically, installs like a membrane element with O rings and a housing, and parallels across vessels for capacity, dominating the packaged ultrapure water skid market. Its trade is per element flow and the maintenance model, elements replaced rather than rebuilt, and its product band is the same megohm class on compliant feed. Between the two architectures the purchase divides by scale and site practice more than by purity, and both quote against the same feed gates and guarantees.

Polarity practice divides the catalog by reversal. Fixed polarity modules run continuous with the electrode streams constant, the classic design, cleaned periodically against scaling and fouling with the vendor's recipes. Polarity reversing designs, the EDR tradition applied to EDI on some product lines, flip the field on a schedule, dislodging scale forming concentration from membrane faces before it hardens, at the cost of a small product upset at each reversal that the train absorbs or valves divert. The choice matters most on marginal hardness feeds where reversal buys forgiveness, and the RFQ should ask which the vendor quotes and what the reversal does to product continuity at the point of use.

Boundaries are worth stating bluntly. EDI is a polish stage: it does not replace reverse osmosis, does not tolerate raw or softened city water alone, and a plant that feeds it such water is buying a fouling calendar. It is not the mixed bed bottle it replaces on every duty: trains needing 18.2 megohm at the point of use, semiconductor final polish for instance, still run exchange or electrodeionization plus finishing, and the upw-system page's train view places the stages honestly. It is not a sterilizer, the ultraviolet sterilizer and filtration stages own the microbial story, and pharma hot water sanitize capability is a specific architecture option to be named, not assumed. The map below compresses the boundaries into one table.

ArchitectureFlow class per unitBest dutyWatch out for
Plate and frame stack5 to 50 m3/h per stack classPower and large industrial trains, rebuild serviceCompression and manifold skill at maintenance
Spiral wound module1 to 10 m3/h per element classPackaged UPW skids, small and mid plantsElement replacement economics at scale
Fixed polarityContinuous DCCompliant feed, stable operationPeriodic cleaning, hardness discipline upstream
Polarity reversingScheduled reversalMarginal hardness forgivenessProduct upset management at each reversal
Hot water sanitize capablePharma and bioprocess ratedSanitizable ultrapure loopsArchitecture and material class to be named
Chapter 4 / 06

Key Specification Parameters

The table below decodes the datasheet lines that decide whether a quoted train delivers megohms on the plant's water. Each row is a purchase defining parameter; the paragraphs after the table explain what to demand and what a weak answer looks like.

AttributeTypical range or optionsWhat it decides
Product flow1 to hundreds m3/h by module countModule count, stack arrangement, and rectifier size
Product resistivity10 to 18 megohm cm at 25 deg CThe headline guarantee on compliant feed
Product silicaSingle digit ppb and below by feedThe anion side performance power buyers watch
Feed hardness gateUnder 0.5 to 1 ppm as CaCO3Scale life of the stack, set by upstream softening or RO
Feed chlorine gateUnder 0.02 to 0.05 ppm freeMembrane and resin oxidative life
Feed CO2Degas above a few ppm by vendor basisAnion load, recovery, and product silica
Temperature band5 to 45 deg C typical quotedConductivity behavior and guarantee conditions
Recovery80 to 95 percent with concentrate routingWater balance and the drain bill
DC power scopeRectifier kW, control basis, reversalEnergy, product continuity, and interlocks
Cleaning and life basisRecipes, interval, module yearsOperating cost and the replacement calendar

The feed gate rows carry the warranty, because EDI guarantees are conditional on feed almost without exception. Demand the vendor's feed specification sheet with the numbers, hardness, chlorine, CO2, iron, temperature, and hold the plant's own analysis against it before the purchase order, with the RO train and any degasser scoped to deliver it. Where the plant's water sits at a gate, the quotation should say so and price the upstream fix, a degasser or a second RO pass, rather than selling modules into a fouling calendar. The vendor who asks for the water analysis first is the one whose megohm numbers mean something.

The product and recovery rows set the acceptance. Resistivity and silica guarantees quote at stated feed, flow, and temperature, measured at the module outlet with the instruments the train carries, and the acceptance test runs on the plant's water, not the datasheet's. Recovery with the concentrate and electrode routing belongs to the water balance, and the energy basis, rectifier draw at design flow, is quoted beside it. The second table compresses the train placement decision the way a specification meeting argues it.

Train and targetConfiguration to specifyCheck before order
Power plant makeup, boiler feed polishPlate and frame stacks after two pass ROHardness and CO2 gates, silica guarantee basis
Microelectronics UPWEDI plus finishing polish to 18.2 megohmPoint of use target, TOC train story
Pharma purified waterSanitize capable modules with UV and filtersSanitization method named, validation support
General industry chemical free DISpiral modules on packaged RO-EDI skidFeed gate compliance on the real water
CO2 heavy single pass RO feedMembrane degasser ahead of EDICO2 basis and recovery math
Water constrained siteConcentrate recycle to RO feedWater balance and silica loop accumulation
Chapter 5 / 06

Selection Decision Factors and RFQ Language

The decision sequence is short enough to run as a specification meeting checklist, and each step eliminates a class of quotations before price comparisons begin.

  1. Write the water story with data: source analysis, the RO stage's actual permeate quality by season, hardness, conductivity, CO2, chlorine, silica, iron, and temperature range, because every gate decision hangs on these numbers.
  2. Fix the product specification: resistivity at 25 deg C, silica, sodium, and any industry expectation, measured at the stated point with the instruments that will police it.
  3. Verify the feed gates against the vendor sheet before architecture: if the water fails a gate, price the upstream fix, degasser, second pass, dechlorination, inside the same evaluation.
  4. Choose architecture by scale and site practice: plate and frame stacks for larger trains and rebuild service, spiral modules for packaged skids, sanitize capability where the industry demands.
  5. Fix the electrical scope: rectifier capacity and control basis, polarity practice and its product upset handling, interlocks and instrumentation.
  6. Fix the water balance: recovery, concentrate and electrode routing, recycle where the site constrains water, and the drain temperatures and flows.
  7. Price the lifecycle: cleaning chemicals and interval, module replacement years against the guarantee, spares strategy, and the vendor's performance support expectations.
  8. Fix the verification evidence: acceptance test on the plant's water with methods, guarantees at stated conditions, and the feed specification sheet as a contract annex.

Against neighboring stages the comparison a specifier needs runs as follows, and it belongs here in the selection chapter rather than in the page title. Reverse osmosis does the bulk removal ahead and owns its element pages. The mixed bed polisher is the incumbent, chemical or service regenerated, and EDI wins where the acid and caustic handling, the exchange bottle logistics, or the continuity between regenerations argue for it, while the mixed bed still takes the final 18.2 megohm polish on the most demanding trains. The upw-system page maps the whole train and treats polish stages at train level, with this page the module authority inside it. UV sterilization and final filtration own the microbial and particle end game. Name the stage boundaries in the RFQ and every vendor quotes the same machine against the same water.

The RFQ block should be written once and reused. A complete block reads: feed analysis with seasonal range and the RO stage basis; product specification with resistivity, silica, sodium, and measurement point; design, minimum, and maximum product flow; architecture proposed with module or stack count and arrangement; vendor feed specification sheet attached as the guarantee condition; electrical scope with rectifier capacity, control basis, and polarity practice; recovery with concentrate and electrode routing and any recycle; materials and sanitize capability where the industry demands; instrumentation list with resistivity, flow, and pressure by point; cleaning regime with chemicals and interval; module life guarantee and replacement basis; and the acceptance test method on the plant's water with conditions stated. A quotation returned without the feed specification sheet or the silica guarantee basis is incomplete at any price.

Chapter 6 / 06

Installation, Standards, Failure Modes, and Maintenance

Installation quality is mostly the water story being true. The RO stage and any degasser commission first and hold their numbers, the feed gates verified on the real plant, then the EDI manifold fills, flushes, and proves its routing, concentrate, electrode, and product streams each going where drawn. The rectifier installs with its interlocks, earths, and the control basis set, and polarity schedules, where the architecture uses them, configure before first power. Instruments calibrate against certified standards, the resistivity at the module outlet and the point of use being the money readings, and the train's data system logs them from the first hour because the guarantee clock runs on evidence.

Commissioning proves the megohms on this water. The acceptance test runs at design flow with feed conditions logged, product resistivity and silica measured by the contracted methods, recovery and energy read against the guarantees, and the train left in the operating state the plant will actually run. Feed gate margins are recorded, hardness and chlorine especially, as the baseline the months ahead will drift against. Operators train on the trend reading, resistivity falling slowly means feed drift or module aging, silica rising alone points the anion side, pressure building means fouling, and the response sequence, check upstream, clean, then escalate, is written into the plant's procedures while the commissioning engineer is still standing there.

Failure modes in service follow a short and predictable list. Scaling heads the list and traces upstream: hardness past its gate deposits on concentrate faces and membranes, product resistivity sags, differential climbs, and the fix is the feed fix plus the vendor cleaning recipe, with repeated events meaning the gate is being paid in module life. Oxidative damage from chlorine excursions, a failed dechlorination or an upstream dosing error, embrittles membranes and resin and shows as permanent quality loss, and it is the unrecoverable one. Fouling with organics and particles, resin fines, colloids past the cartridge filters, raises differential and drags performance, answered by filtration discipline and cleaning. Electrical faults, rectifier drift and electrode stream starvation, degrade the field that does the work, found by current and product trend together. Temperature and flow excursions outside quoted bands simply void the arithmetic, and the instrumentation that would have caught them is the cheap insurance the train carries anyway.

Maintenance intervals scale with feed compliance more than with hours. A train holding its gates runs cleanings annually or less, modules six to ten years by vendor and water, and the calendar is instruments and gaskets. A train flirting with its gates runs cleanings quarterly and buys modules on a schedule nobody budgeted, which is the entire economic argument for the upstream scope. Instrument calibration, the resistivity and silica and flow readings that prove the product, follows the pure water calendar, and the cleaning chemicals stock belongs to the spares budget with the gaskets and O rings. Every campaign produces numbers, resistivity and silica trend against feed, differential, cleaning outcomes, and those numbers calibrate the next RFQ and the next gate review, which is how a purchasing file gets smarter instead of just older.

FAQ

Can EDI feed on anything besides RO permeate?

Practically no. The technology is a polish stage with feed gates in the parts per billion: hardness under roughly 0.5 to 1 ppm as CaCO3, free chlorine under 0.02 to 0.05 ppm, iron and manganese in the low ppb, all delivered by RO on softened or suitable water, optionally with a second pass or degasser. Feeding softened tap water or single pass RO with high CO2 directly buys a fouling and scaling calendar paid in module life, and the vendor's feed specification sheet is the guarantee condition for exactly that reason.

What resistivity and silica will EDI deliver?

On compliant feed, 10 to 18 megohm centimeter at 25 deg C is the healthy product band, with silica polished to single digit parts per billion and below from tens of ppb feed. The guarantees quote at stated feed, flow, and temperature, and the acceptance test runs on the plant's water with agreed methods. The absolute 18.2 megohm ceiling belongs to final finishing stages on the most demanding trains, not to the module outlet claim.

How does EDI avoid regeneration chemicals?

The DC field does the regenerating. At the resin membrane interfaces in the dilute chambers, water splits into hydrogen and hydroxide ions that regenerate the ion exchange sites in place, the same chemistry an acid and caustic regeneration delivers, produced electrically and continuously. That is why the module runs for years between cleanings and the plant takes no acid or caustic deliveries for polish duty.

Plate and frame or spiral wound modules?

By scale and site practice more than purity, both deliver the same megohm class on compliant feed. Plate and frame stacks serve larger flows per unit and rebuild service, the power and large industrial tradition. Spiral wound modules package like membrane elements in pressure vessels, dominate the packaged skid market, and replace as elements. Choose the maintenance model the plant actually operates.

Why does carbon dioxide matter so much?

Because CO2 crosses into the anion side as load, consuming the capacity that would polish silica and other weak ions, dragging recovery and product silica with it. Single pass RO on alkaline water can pass tens of ppm of CO2, which is why trains on such water put a membrane or chemical degasser between RO and EDI, and the feed basis in the RFQ states the CO2 the design assumes.

What kills EDI modules?

Two things, one recoverable, one not. Scaling from hardness past its gate deposits on membranes and concentrate faces and responds to cleaning if caught, repeated events spend module life. Chlorine and oxidant excursions embrittle membranes and resin permanently, and no cleaning reverses it. Both trace upstream, which is why the purchase decision includes verifying the gates on the real seasonal water and pricing the upstream scope that holds them.

How is an EDI purchase accepted?

A performance test on the plant's own water at design flow, with feed conditions logged against the vendor's feed sheet, product resistivity and silica measured by contracted methods at the module outlet, and recovery and energy read against the guarantees, followed by a trending period that confirms the numbers hold. The feed specification sheet travels as a contract annex, because every guarantee in the quotation is conditional on it.

Sources

  1. DuPont Water, Electrodeionization (EDI)
  2. DuPont, EDI-310 Module
  3. Veolia Water Technologies, E-Cell Electrodeionization (EDI) Solutions