Climbing-formwork anchors should be selected from the project-specific wind uplift and the climbing system’s approved capacity, not from dead load alone.
The calculation must cover the brackets, formwork, platforms, live load, concrete pressure, construction tolerances, and wind exposure at each lift position.
Separate Dead Load from Wind Uplift
Climbing brackets attached to preset anchors transfer the dead load of the wall formwork and brackets together with wind loads into the supporting structure [S1]. Dead load may include the self-weight of the formwork, bracket assembly, working platform, reinforcement, and stored materials.
The climbing brackets transfer the wind loads and dead load of the wall formwork and brackets to preset anchors [S1]. The project calculation should therefore separate vertical gravity load from horizontal wind action and include the resulting moment rather than adding wind pressure directly to the anchor’s vertical demand.
The published Hünnebeck self-climbing system states a vertical load capacity of up to 150 kN per bracket and refers to a maximum influence width [S3]. These figures describe that system, not a generic anchor rating.
Build the Wind Load from the Exposed Envelope
The first calculation step is to define the area exposed to wind at the most unfavorable lift stage, including shuttering, platforms, braces, and any gap between the system and the structure. The design wind pressure and code-defined shape factors should then be applied to that area. [S1]
Anchor spacing is controlled by that wind action. This is a conditional design result: increasing spacing without recalculating uplift, eccentric loading, and system stability is not permitted by that statement.
Wind speed is also a system limit rather than an anchor-selection shortcut. Engineers must separate the wind-resistance test from the site-specific design load, because tested capability does not establish the anchor force for a particular building geometry.
Compare the Main Anchor-Load Cases

Anchorage design should compare at least four cases: static vertical load during concreting, horizontal wind load while stationary, load during climbing, and the most adverse partially released condition. Each case must include the associated eccentricity and the condition of the supporting concrete. [S1]
The comparison shows why one axial capacity cannot cover every operating condition. A system may satisfy the 150 kN vertical criterion while still requiring checks for wind-induced shear, tension, moment, concrete breakout, and anchor-group eccentricity [S3].
Use the System Design as the Anchor Envelope
Climbing systems are supplied with structural calculations that define anchor positions, loads, reinforcement, and installation conditions. The Doka 150F documentation includes separate sections for structural design, loading data, anchoring on the structure, positioning points, and suspension points [S5].
An engineer should extract the allowable actions at the actual anchor or lifting point rather than treating the system’s vertical load rating as a universal anchor capacity. The position of the anchor, cone engagement, embedded depth, concrete strength, edge distance, and bracket arrangement can all change the available resistance.
The method statement for the PERI CB 160 instructs users to mount wind bracing when required and identifies the leading-anchor operation as part of closing the formwork [S2]. That sequence confirms that wind restraint and anchor placement are tied to the climbing cycle, not independent site additions.
Verify Concrete, Engagement, and Installation

Anchorage capacity is only meaningful when the concrete and installation match the design assumptions. The anchor position must be surveyed, reinforcement must not conflict with the climbing cone or anchor, and the concrete must reach the specified strength before loading. [S5]
This is a workmanship-critical limit, and a torque or engagement check should be recorded rather than relying on visual inspection alone.
Concrete cover, embedment depth, edge distance, hole cleanliness, and allowable bearing or pullout conditions must be checked against the approved anchor design. Where an existing structure is involved, the climbing method statement requires a positioning point and a safe suspension point, with separate instructions for other anchorages and retrofitted suspension points [S5].
Who Should Own the Anchor Decision
The anchor calculation is for the temporary-works engineer or formwork designer working with the climbing-system supplier. The contractor must implement the approved design, while the supplier remains responsible for the system-specific instructions and structural data. [S5]
It is not appropriate for a site team to select anchors from concrete pull-out test data alone. The governing checks must represent the complete load path through the bracket, anchor, concrete, reinforcement, and supporting wall, including wind-induced eccentricity. The general climbing formwork reference covers the wider system, while climbing formwork platform load capacity addresses a distinct platform-loading question.
Document Inputs Before Release

A defensible anchor package should include the design wind speed and pressure assumptions, exposed areas, gross and net dead loads, platform live loads, concrete-pressure effects, anchor coordinates, edge distances, concrete strength, and each load combination. [S1]
The package should also identify the allowable load at each anchor point, distinguish static from climbing loads, and define inspection criteria for cone engagement, anchor setting, concrete strength, and concrete damage. Any change in formwork height, bracket spacing, platform layout, or climbing direction requires the wind and anchor checks to be revisited, particularly because the published system geometry allows different configurations, including 3.20 m working platforms, 2.30 m trailing platforms, and 1.50 m pouring platforms [S3].
The next trackable approval is the issued temporary-works design showing each anchor’s calculated tension, shear, and moment demand against the system-specific allowable actions, followed by site records confirming concrete strength and full stop-anchor engagement [S5].