Heat Recovery Steam Generator

A heat recovery steam generator, HRSG, is the boiler that raises steam from the hot exhaust of a gas turbine or a similar process source: gas flows across banks of finned tubes arranged as heat transfer sections in the temperature ladder, superheaters first, then evaporator sections, then economizers, and the recovered heat feeds a steam turbine, a process host, or both. Machines are built with multiple pressure levels, high, intermediate, and low pressure circuits each with its own drum, economizer, evaporator, and superheater, because a single level cannot chase the exhaust temperature profile efficiently, and thermal design is written in pinch and approach terms, the small temperature differences that trade surface area against steam production. Supplementary duct firing adds burners between the turbine exhaust and the first sections for steam beyond the unfired recovery, and selective catalytic reduction for NOx control often lives in the gas path where its temperature window fits.

Procurement engineers meet these machines on combined cycle power plants from tens to hundreds of megawatts, on cogeneration sites feeding process steam, on refinery and petrochemical hot oil and process exhaust recovery, and increasingly as the flexible steam source behind fast cycling gas turbines on renewable heavy grids. The decision this page settles is which architecture fits the duty: horizontal gas path with vertical tubes and natural circulation, or vertical gas path with horizontal tubes, and natural circulation against once through OTSG circuits, how many pressure levels the economics want, whether duct firing belongs, and what cycling and emissions scope the machine carries. The answer lands as an RFQ line set, exhaust conditions, steam requirements, pinch basis, circulation type, and firing and SCR scope, and every chapter below feeds that line set so the HRSG recovers the steam the project sells rather than the steam a catalog promises.

Industrial heat exchanger installation showing tube bundles and frames in a plant room, the extended surface heat recovery equipment class whose large scale finned tube harps heat recovery steam generators are built from

Photo: Renegade, Public domain, via Wikimedia Commons

This page treats the heat recovery steam generator as a purchasing object: how pinch and approach economics size the sections, how horizontal and vertical machines and natural against once through circulation divide the duties, what multi pressure architecture and duct firing buy, how SCR and emissions scope integrate, and how the whole decision folds into a defensible RFQ with cycling and inspection deliverables included. It is written for engineers who issue specifications on recovery boiler equipment, not for readers who want a brochure summary.

Chapter 1 / 06

What an HRSG Is and What Is Being Decided

The defining act of the machine is steam from exhaust, a boiler with no fired furnace of its own in its unfired form. Gas turbine exhaust arrives at 450 to 620 deg C and several hundred thousand kilograms per hour on utility machines, the HRSG passes it across finned tube harps and modules in descending temperature order, and each working fluid stream finds its heat at its level: superheater and reheat surfaces at the hot end, evaporators in the middle where the steam is made, economizers and feedwater preheat at the cold end, and condensate or fuel gas heaters last where plants squeeze the final degrees. The result is a steam generator whose fuel was already paid for by the gas turbine, which is why every degree of exhaust left in the stack is money the project spent and did not collect.

What is being decided in this purchase is five commitments at once. First an architecture: horizontal gas path with vertical evaporator tubes and natural circulation, the combined cycle standard, or vertical gas path with horizontal tubes, each with its plot and cycling story, and within them natural circulation drums against once through circuits. Second a pressure level structure: single, dual, or triple pressure with reheat, sized by the steam turbine or process host economics, with the drums or once through separators each level implies. Third a thermal basis: pinch and approach targets at the guaranteed exhaust conditions, the steam flows and temperatures at each level, and the stack temperature the economics accept. Fourth a firing and emissions scope: unfired, limited supplementary duct firing, or full fired capability, and SCR and carbon monoxide catalyst placement in the gas path. Fifth a duty envelope: baseload or cycling service with starts and ramps guaranteed, fast start capability where the grid wants it, and the inspection and maintainability provisions that follow. A quotation that leaves any of the five to later detail is a module drawing, not a machine.

Against its neighbors the HRSG occupies precise ground. The economizer page covers the feedwater heat recovery surface of conventional fired boilers, one heating surface, and the economizer is literally one component inside this machine, not this machine. The steam drum page covers the vessel each pressure level of a drum type HRSG carries, and the industrial burner page covers the combustor of a duct burner's fired cousin, the duct burner itself being a component scoped inside this purchase. The surface condenser and air-cooled condenser pages close the steam cycle the HRSG feeds. A waste heat boiler on process exhaust, sulfur or reformer service, is the same species bought against process sources, and this page's Types discussion covers it as the WHB tradition rather than opening a second leaf. The recovery boiler of a pulp mill is deliberately not this machine, it burns black liquor as fuel in a furnace, and this page marks that boundary plainly. Naming the neighbors keeps vendors quoting the same machine against the same exhaust.

Standards and references frame the datasheet. HRSG practice is written in the power boiler and pressure part codes, ASME Section I with its piping and drum code context for the pressure parts, and the associated construction references for finned tube modules, harps, and casings, with CEN equivalents in the European market. Performance is argued in guaranteed numbers at guaranteed exhaust conditions, steam flows and pressures and temperatures by level with the exhaust conditions and the methods named, and acceptance testing follows the heat exchanger and boiler test traditions with the turbine cycle context. Duct firing burners carry their combustion equipment standards, and SCR systems carry their catalyst and reagent practice. A datasheet that quotes steam flow with no exhaust basis and no pinch statement is a price tag, not a specification.

The station around the HRSG deserves naming in the RFQ too. The gas turbine exhaust delivers through a transition duct with its expansion and damping, and a bypass stack and damper where the operating philosophy wants turbine operation without the boiler. Feedwater arrives from the deaerator through the boiler feed pump train, and each pressure level's economizer feeds its drum or separator with the level transmitter loops that run them. Steam leaves each level to the turbine or process header, with a desuperheater trimming where control needs it, and the safety relief valve count the code requires per level. Duct burners bring their gas train with safety shutoff valves and flame supervision. The SCR carries its reagent system, ammonia or urea, with its injection grid and the catalyst modules, and the stack instrumentation closes the emissions record. Buying the HRSG without its interfaces is how combined cycle commissioning schedules die.

Chapter 2 / 06

How Pinch, Approach, and Pressure Levels Write the Design

Pinch point is the small temperature difference at the closest approach between the gas and the evaporating fluid, where the gas leaving the evaporator meets the saturated steam temperature, and it is the main lever of HRSG economics. A tight pinch, 8 to 15 kelvin common in modern unfired machines, extracts more steam from the same exhaust at the price of surface area, because the heat transferred per degree of driving force shrinks as the curves close. A wide pinch saves capital and leaves heat in the stack. Approach temperature plays the same role between the economizer outlet water and the saturation temperature, commonly 5 to 15 kelvin, tight enough to use the surface, loose enough to avoid steaming the economizer at low loads, a behavior the design must handle where it occurs. The pinch and approach lines belong in the RFQ as stated design bases, because two HRSGs with identical steam numbers can be different machines underneath.

Pressure levels are the efficiency answer to the exhaust temperature profile. A single pressure machine takes its steam at one saturation temperature, and the gas cools toward that one level, leaving a stack temperature the economics may not forgive. A dual pressure machine adds an intermediate or low pressure circuit, evaporating at a lower temperature to chase the gas further down, and a triple pressure with reheat machine, the utility standard for large combined cycles, recovers at three levels and reheats the steam turbine's high pressure exhaust back up, moving overall cycle efficiency into the sixty percent class with the gas turbine. Each added level costs drums or separators, piping, and control complexity, and earns its keep from the steam turbine's expanded work and the colder stack. The buyer states the steam host's requirements and lets the level structure be an evaluated bid outcome with the lifecycle math shown, which is exactly how serious HRSG procurements are run.

Circulation type divides the evaporator physics. Natural circulation, the dominant architecture, relies on density difference between downcomer water and riser mixture in circuits sized to circulate reliably from low load to high, with drums separating the steam, the steam drum page's machine at each level, and the virtues of thermal inertia, tolerance of water chemistry upsets, and simple internals. Once through circuits, OTSG style, pump feedwater through the tubes to complete evaporation and a degree of superheat in a single pass, with no drum, thinner walls and smaller water inventory, and the fast load and start capability that cycling and peaking duty rewards, at the price of water chemistry sensitivity, since every impurity concentrates in the pass rather than a drum, and more demanding controls. Forced circulation hybrids add circulation pumps to vertical path designs where natural head is awkward. The cycling requirement of the plant writes this line, starts per year and ramp rates, and the once through economics are argued against the drum machine's tolerance and simplicity.

Gas side pressure drop is steam the turbine pays for. Every harp, catalyst layer, and duct restriction across the HRSG raises the gas turbine back pressure a fraction, and gas turbine output falls with it, roughly following the compressor and turbine matching physics, fractions of a percent of output per inch of water. The RFQ states the allowed gas side pressure drop, commonly 3 to 5 kilopascals class across unfired machines by size, and the vendor's area optimization spends it, because an HRSG can always buy performance by tightening pinch if the turbine pays the drop for it. The trade is explicit in good bids, area and pinch against gas side drop and turbine output, and the buyer who sees only steam numbers is not seeing the machine.

Duct firing rewrites the whole profile when it runs. Supplementary burners between the exhaust duct and the hot end add 100 to 300 kelvin and more to the gas entering the superheaters, and steam output climbs toward double the unfired figure on fully fired machines, with the sections behind the fire working harder and the stack hotter, and the metallurgy of the hot end tubes and the casing upgraded for the fired temperature. Firing changes the economizer steaming and drum circulation behaviors at its edges, drives the SCR window management, and writes its own burner management logic with the fuel train and flame supervision of any fired equipment. The fired scope is bought as capability with guarantees at named firing rates, and the unfired and fired performance cases both belong in the contract because the plant runs both.

Chapter 3 / 06

Architectures, Firing, and Duty Boundaries

The horizontal gas path machine is the combined cycle standard: gas flows horizontally through module after module, evaporator tubes run vertical in natural circulation circuits, drums sit above at each pressure level, and the plot is long rather than tall. Horizontal machines draft naturally into drum type natural circulation, ride load changes on the drum inventory's thermal inertia, and open their modules to the side for access. The vertical gas path machine, the traditional alternative, passes gas upward with horizontal tube banks, suits tight plots and rooftop and marine installations, and tends toward forced or once through circuits where natural head does not fit, with its own maintenance access story on the vertical stack. Both are built across the size range, and serious bids argue plot, cycling, and access rather than dogma.

The once through OTSG is the architecture of the cycling decade. With no drums and small water inventory in serpentine circuits, the machine heats, pressurizes, and steams fast, following gas turbine ramps in minutes rather than the drum machine's careful warmup, and start cycles measured in hundreds per year are its native duty rather than its fatigue problem. The costs are the chemistry discipline, full flow condensate polishers or equivalent feedwater purity, since the pass concentrates what it receives, and the control sophistication of a machine whose evaporator ends move with load. Drum machines answer the cycling demand with designed fatigue provisions, thicker margins, drains and vents automation, and start sequence optimization, and the bid comparison on cycling duty shows both answers with starts per year and ramp guarantees written down.

Firing scope and emissions hardware complete the architecture. Unfired machines stop at recovery, and their hot end runs at turbine exhaust temperature. Supplementary fired machines add duct burners for peaking steam, limited firing keeping the hot end in the recovered metallurgy class, and fully fired machines run the hot end to fired boiler temperatures with the casing and tube upgrades implied. The SCR, where the permit requires it, sits in the gas path at the temperature window the catalyst wants, commonly between the HP evaporator and economizer sections on unfired machines or downstream of the firing where supplementary heat stabilizes the window, with carbon monoxide catalyst near the hot end where it is specified, and the reagent system and ammonia injection grid arriving as skid scope. The emissions layout is decided with the HRSG because it moves sections and costs drop, and a retrofit SCR is a rebuild wearing a permit.

Boundaries are worth stating bluntly. This page owns the HRSG as a machine and treats the waste heat boiler on process exhaust as the same species under its Types discussion, not a second leaf. The economizer is one surface inside this machine, with its own page for its fired boiler duties, and the duct burner is a component here, with fired equipment practice referenced rather than doubled from the burner page. The steam drum belongs to the drum machine's levels, its own page as a vessel. A pulp mill recovery boiler is a fired boiler burning black liquor fuel, not an exhaust recovery machine, and the BLRBAC tradition and its incident literature are another world. Condensing the boundaries, the map below is the one table a specifier scans before the RFQ.

ArchitectureCirculationBest dutyWatch out for
Horizontal gas path, multi drumNatural circulationCombined cycle baseload, process cogenerationPlot length, drum warmup on deep cycling
Vertical gas pathForced or once throughTight plots, roof and marine, fast responseAccess heights, circulation pump scope
Once through OTSGOnce through serpentineFast cycling, frequent starts, peaking dutyFeedwater purity discipline and controls
Supplementary firedDuct burners addedSteam peaking beyond unfired recoveryHot end metallurgy, burner management scope
With SCR and CO catalystLayers in the gas pathPermit driven NOx and CO controlWindow management with firing, reagent skid
Process waste heat boilerBy source chemistryReformer, sulfur, and process exhaust recoverySource specific fouling and materials
Chapter 4 / 06

Key Specification Parameters

The table below decodes the datasheet lines that decide whether a quoted HRSG recovers the steam the project sells. Each row is a purchase defining parameter; the paragraphs after the table explain what to demand and what a weak answer looks like.

AttributeTypical range or optionsWhat it decides
Exhaust mass flow and temperatureGuaranteed with turbine basis and H2 plansThe whole heat account and every section's size
Pressure levels and reheatSingle, dual, triple with reheatCycle efficiency, stack temperature, and machine cost
Steam output by levelFlow, pressure, temperature per levelThe product, guaranteed at the exhaust basis
Pinch and approachPinch 8 to 15 K; approach 5 to 15 KSurface area against steam recovery economics
Stack temperature80 to 160 deg C by fuel and dew pointThe recovery floor and cold end materials
Gas side pressure drop3 to 5 kPa class by sizeGas turbine output spent on the HRSG
Circulation typeNatural with drums, forced, once throughCycling capability, chemistry tolerance, controls
Duct firing scopeUnfired, limited, or fully fired ratesPeaking steam and hot end metallurgy
Emissions scopeSCR and CO catalyst placement and reagentPermit compliance built into the machine
Cycling guaranteesStarts per year, ramp rates, life basisFatigue provisions and warmup automation

The exhaust and pinch rows carry the guarantee logic. Demand the steam numbers tied to a stated exhaust flow and temperature, with the gas turbine reference condition named, because the same HRSG makes different steam behind different turbine days, and hydrogen firing plans on the turbine belong in the basis if the project has them, since firing changes the exhaust. Pinch and approach should be stated as design values, and the bid comparison prices them, tighter pinch buying steam with area and gas side drop. A quotation that guarantees steam without the exhaust basis is selling weather.

The circulation and cycling rows set the duty character. Natural circulation drum machines state their start and ramp behavior against fatigue design provisions, and once through machines state their water chemistry requirements and control scope, with the condensate polisher or feedwater purity basis explicit. The fired and emissions rows carry the permit: firing rates with performance at each, SCR window management across the firing range, and reagent system scope. The second table compresses the duty decision the way a specification meeting argues it.

Duty profileArchitecture to specifyCheck before order
Combined cycle baseload, efficiency drivenHorizontal triple pressure with reheatPinch and cycle math, stack dew point basis
Daily cycling, hundreds of startsOnce through or fatigue designed drumStart guarantee and warmup automation basis
Process cogeneration, steam host ledDual pressure with duct firing for swingFired case guarantees and host steam spec
Permit with SCR and CO limitsCatalyst placement in the original designWindow management across firing range
Tight plot or rooftopVertical gas path machineAccess plan and structural interface
Reformer or process exhaust recoveryProcess waste heat boiler per sourceSource chemistry, fouling, and materials basis
Chapter 5 / 06

Selection Decision Factors and RFQ Language

The decision sequence is short enough to run as a specification meeting checklist, and each step eliminates a class of quotations before price comparisons begin.

  1. State the exhaust source honestly: gas turbine model and its guaranteed exhaust flow and temperature, or the process source with its chemistry and fouling, including any hydrogen firing plans on the turbine that change the exhaust basis.
  2. State the steam market: turbine or process host requirements by level, flow, pressure, and temperature, and the value of an extra ton per hour, because that number prices every pinch and level decision.
  3. Choose the architecture by plot and wind of duty: horizontal natural circulation for baseload and plot length, vertical for tight sites, once through for cycling duty with its chemistry costs accepted.
  4. Fix the thermal basis: pinch and approach stated, stack temperature with its dew point logic, gas side pressure drop allowance, and performance guarantees tied to the exhaust basis at named conditions.
  5. Scope the firing: unfired, limited, or full supplementary with performance at each firing rate and the hot end metallurgy basis stated.
  6. Scope the emissions: SCR and CO catalyst placement with window management across the firing range, reagent system, and the stack instrumentation the permit reads.
  7. Set the cycling guarantees: starts per year, ramp rates, warmup sequences and their automation, and the fatigue provisions behind them.
  8. Fix the verification evidence: performance test method, module and pressure part documentation to the code basis, and the inspection and access provisions for the maintenance life.

Against neighboring equipment the comparison a specifier needs runs as follows, and it belongs here in the selection chapter rather than in the page title. An economizer is one surface inside this machine, a fired boiler's water side recovery, and not the HRSG. A steam drum is a component per pressure level, its own page's vessel. A surface condenser or air-cooled condenser closes the cycle this machine feeds, and the deaerator and boiler feed pump deliver its water. A pulp recovery boiler burns liquor fuel in a furnace and is a different machine on a different page. The waste heat boiler tradition on process exhaust is this species applied to process sources and is covered here as a type rather than a second leaf. Name the neighbors in the RFQ and every vendor quotes the same machine against the same exhaust.

The RFQ block should be written once and reused. A complete block reads: exhaust source with guaranteed flow, temperature, and pressure at the HRSG inlet, including hydrogen plans where they exist; steam requirements by pressure level with reheat where the cycle has it; architecture and circulation type proposed with plot basis; pinch, approach, stack temperature, and gas side pressure drop as stated design values; steam output guarantees by level at named exhaust conditions with the test method; duct firing scope with guarantees at each firing rate; SCR and CO catalyst scope with placement and reagent system; cycling guarantees with starts and ramps and fatigue basis; pressure part code basis with documentation deliverables; feedwater and chemistry basis with the polisher scope where once through; bypass stack and damper philosophy where the operating case wants it; structural, duct expansion, and acoustic interfaces; instrumentation list by level including drums, level transmitters, and the emissions train; and the inspection and access provisions. A quotation returned without the exhaust basis or the pinch statement is incomplete at any price.

Chapter 6 / 06

Installation, Standards, Failure Modes, and Maintenance

Installation quality is a project in itself, because an HRSG is large module steel and pressure parts assembled into a gas tight casing. Modules lift and set by plan, harps and drums placed with the sequence the shipping splits imposed, and the casing, expansion joints, and stack go up around them with the gas tightness discipline the performance test will judge. Piping by level, main steam and reheat with their supports and the desuperheater scope, feedwater from the boiler feed pump train, and the blowdown and vent systems, follows the pipe analysis. Duct burners install with their gas train, safety shutoff valves, and flame supervision proven to the burner management logic. The SCR reagent skid and injection grid commission with the catalyst loaded per the layout the design fixed, and the whole gas path proves tight before the first fire.

Commissioning proves steam and emissions at the exhaust the contract named. The performance test runs the unfired case first, steam by level against guaranteed exhaust conditions with the methods agreed, then the fired cases at their rates, and the emissions train reads the SCR performance across the range. The cycling behaviors prove where the contract guarantees them: start sequences run with the drums or once through controls as designed, ramps watched against the fatigue basis, and the drain and vent automation doing its part. Chemical cleaning and the feedwater chemistry program commission before load per the code and vendor practice, because the machine's first weeks set its internal surfaces' tone, and the steam purity targets by level are verified with the sampling the cycle expects.

Failure modes in service follow a short and predictable list. Fatigue at the cycling points, tube to header welds, drum penetrations, and casing attachments on machines started hard and often, is the headline, and the fatigue provisions bought or not bought at specification are what the inspection findings reflect. Fouling of the finned surfaces, gas side deposits from turbine operation, duct firing, and the environment, raises gas side pressure drop and steals turbine output quietly, answered by washing with the access the module layout provides. Economizer steaming at odd loads and drum level misbehavior trace to the approach design and the controls, and the level transmitter loops by level get the calibration the safety function they feed deserves. Catalyst aging raises NOx or CO until the permit notices, with replacement scheduled on activity trend, and reagent carryover into the stack plume, ammonia slip, is managed by the injection tuning. Duct burner problems are the fired equipment list, flame stability and tube impingement first, and hot end metallurgy questions follow the firing hours. Valve and instrument faults distribute across the levels and the emissions train as ordinary plant wear.

Maintenance intervals scale with duty and firing more than with calendar. Baseload unfired machines run long campaigns with module inspection at the major outages, thickness and fatigue surveys at the designed points, and catalyst activity tracked to its replacement curve. Cycling machines shorten the fatigue inspections to the starts the guarantee counted, and the wash scope follows the fouling the turbine and firing produce. Every level's drums or separators get their internal inspection at the boiler calendar, and the chemistry program, silica and conductivity by the steam drum page's logic, is the daily maintenance nobody sees until it stops. Every outage produces numbers, steam against exhaust, drop against clean, fatigue findings against the basis, and those numbers calibrate the next RFQ, which is how a purchasing file gets smarter instead of just older.

FAQ

How many pressure levels should my HRSG have?

Let the steam market decide. Single pressure serves simple process steam, dual pressure chases the exhaust further for cogeneration economics, and triple pressure with reheat is the utility combined cycle standard that moves cycle efficiency into the sixty percent class with the gas turbine. Each level adds drums or separators, piping, and control, and earns its keep in steam turbine work and stack temperature, so make it an evaluated bid outcome with the lifecycle math shown.

What pinch point should I specify?

Modern unfired machines commonly run 8 to 15 kelvin pinch, tighter buying more steam from the same exhaust with more surface area and gas side drop. The pinch is an economics dial, not a virtue, so state it as a design value, price the steam it buys against the area and the gas turbine output it spends, and let the bid show the trade. Two HRSGs with identical steam numbers and different pinches are different machines underneath.

Natural circulation drums or once through OTSG?

Drum machines carry thermal inertia, chemistry tolerance, and simple internals, the baseload and process virtues, and answer cycling duty with designed fatigue provisions. Once through machines carry small water inventory, fast starts, and ramp following for hundreds of starts per year, at the price of feedwater purity discipline and sophisticated controls. The starts per year and ramp requirements of the plant write this line, and both answers are honest when the guarantees behind them are.

Does duct firing change the machine I buy?

Yes, structurally. Supplementary firing adds duct burners with their gas train and flame supervision, raises the hot end temperatures toward fired boiler class, upgrades the metallurgy and casing for it, and shifts the SCR window the design must manage. Buy the firing scope as capability with guarantees at named rates, because the fully fired case is a different hot end than the unfired machine wearing an option label.

Why does gas side pressure drop matter so much?

Because the gas turbine pays it. Every kilopascal of HRSG resistance raises turbine back pressure and costs output and heat rate on the machine that makes the electricity, so the allowed drop, commonly in the 3 to 5 kilopascal class by size, is a purchase line the vendor spends in the pinch optimization. An HRSG that buys performance by tightening pinch while widening the drop may be improving itself at the turbine's expense, which is why the trade belongs in the bid comparison.

Can an HRSG serve a non turbine exhaust source?

Yes, that is the waste heat boiler tradition inside this page's Types discussion, reformers, sulfur units, and process exhausts recovered by the same finned tube and pressure part architecture, sized against the source chemistry and fouling rather than a turbine's clean exhaust. The source's fouling and corrosion behavior moves to the front of the specification, and the machine is engineered to the source, not adapted from a catalog combined cycle module.

What cycling guarantees should the contract carry?

Starts per year with the start type named, hot, warm, cold, ramp rates in percent per minute by level, warmup and drainage automation scope, and the fatigue design basis behind them, with inspection provisions that read the fatigue points over life. Cycling capability is hardware and sequence engineering, not a brochure adjective, and the guarantee that matters is the one the inspection schedule can check against.

Sources

  1. Nooter/Eriksen, Heat Recovery Steam Generators
  2. John Cockerill Energy, H2 ready Heat Recovery Steam Generators
  3. John Cockerill Energy, HRSG Brochure (PDF)