Fired Heater

A fired heater is a direct fired piece of process equipment in which burners release heat inside a refractory lined box or cylinder, and a process fluid flowing inside tubes absorbs that heat as it passes through a radiant section and usually a convection section above or behind it. API Standard 560 is the purchasing and design reference the petroleum industry writes these machines in, and its vocabulary, radiant average heat flux, tube metal temperature, bridge wall and stack conditions, draft class, defines the datasheet rows this page explains. Duties run from a few megawatts on small specialty process heaters to over one hundred megawatts on crude and vacuum units and steam methane reformers, with process fluids from natural gas to resid, thermal oil, and boiler feedwater preheat, and outlet temperatures from 200 to over 900 deg C depending on service.

Procurement engineers meet these units on refinery charge and reboiler service, gas plants and ethylene crackers, chemical plant hot oil loops, reforming and hydrogen plants, and any duty where steam and hot oil temperatures cannot reach or where direct firing is the economic answer. The decision this page settles is which heater geometry and firing arrangement fits the fluid and its coking or cracking limits: cabin or box, cylindrical, or vertical cylindrical with helical coils, natural, forced, or balanced draft, and whether a combustion air preheater belongs in the project. The answer lands as an RFQ line set, duty and flux and tube metallurgy and draft and emissions, and every chapter below feeds that line set so the heater is bought against the process it serves rather than against a furnace catalog. This page is the tube fired process heater authority: the burner that fires it is covered by its own page, and melting and heat treatment furnaces, which heat workpieces rather than fluids in tubes, are different machines entirely.

Gas fired industrial furnace in operation with workers guiding an ingot at the opening, the fired process equipment class to which API 560 cabin and cylindrical process heaters belong with burners firing into a radiant chamber

Photo: BiblioArchives / LibraryArchives (Library and Archives Canada), CC BY 2.0, via Wikimedia Commons

This page treats the fired heater as a purchasing object: how radiant flux and tube metal temperature limits size the box, how cabin, cylindrical, and vertical coil geometries divide the duties, how draft and combustion air preheat set efficiency, what API 560 expects a datasheet to carry, and how the whole decision folds into a defensible RFQ with burner management and emissions scope included. It is written for engineers who issue purchase specifications on fired process equipment, not for readers who want a brochure summary.

Chapter 1 / 06

What a Fired Heater Is and What Is Being Decided

The defining act of the machine is heat release by combustion transferred across tube walls to a process fluid. Fuel gas or oil fires through burners into a radiant chamber, flame and hot gas irradiate the tube surfaces at high flux, and the combustion gas then gives up its remaining heat to convection section tubes, often with steam generation or feed preheat coils and an economizer or air preheater economizing the last of it, before the induced draft system sends it up the stack. The fluid never sees the fire, which is why the tube wall is the critical component of the entire plant: too hot a wall and the fluid cokes or cracks inside the tube, fouling the pass and raising the wall further in the spiral every heater engineer fears. Everything in the specification exists to keep tube metal temperature inside the envelope the fluid chemistry allows.

What is being decided in this purchase is five commitments at once. First a duty and an outlet condition, because the heater must deliver flow and temperature with the pressure drop the process allows. Second a flux and metallurgy envelope, radiant average flux commonly in the 20 to 45 kilowatt per square meter band by service with peak local flux managed by burner placement, and tube materials from carbon steel through the 1 and 1 quarter and 2 and 1 quarter chrome families to 9 chrome and austenitic and high alloys as tube metal temperature climbs. Third a geometry and draft arrangement, since cabin, cylindrical, and vertical helical layouts each fit different duties and plots, and natural, forced, and balanced draft change fan scope and air infiltration. Fourth an efficiency and emissions package, with or without combustion air preheat, and NOx and CO and particulate limits set by the permit. Fifth a safety and control basis, burner management with flame supervision and the fuel trip logic the code requires. A quotation that leaves any of the five as later detail is a drawing, not a machine.

Against its neighbors the fired heater occupies precise ground. The industrial burner is the combustor component inside it, and burner vendors quote under the heater specification, not the reverse. A melting furnace or heat treatment furnace heats a workload directly and belongs to casting and thermal process equipment families, not to this page. An electric immersion heater or a steam heated exchanger serves low and medium temperature duties where firing is unnecessary, and the selection chapter contrasts them honestly: fired heat earns its capital and its flame risk only above the bands steam and hot oil reach economically, or where duty is large and fuel is cheap. A heat recovery steam generator makes steam from gas turbine exhaust and has no firebox of its own unless duct fired. A thermal oxidizer destroys pollutants rather than heating a process stream, though it shares burner and stack hardware vocabulary. Naming the neighbors in the RFQ keeps every vendor quoting the same machine.

Standards organize the datasheet, and API 560 is the spine for petroleum service: it fixes the datasheet content, design considerations for radiant and convection areas, tube and header materials practice, refractory and casing expectations, stack and draft, instrumentation, and the inspection and testing regime a purchaser should expect. Tube design stress practice draws on API 530, the calculation of heater tube thickness and life, and construction code context comes from ASME Section I or VIII depending on service. Burner management follows NFPA 85 or 86 style practice with safety shutoff valves, purge, and flame supervision by a flame detector on each burner. Efficiency testing follows API 560 appendix practice with excess air and exit gas temperature as the measured quantities. A datasheet that quotes none of these references is a price tag, not a specification.

The station around the heater deserves naming in the RFQ too. Fuel systems bring gas through pressure regulation and safety shutoff valves to the burners, with a flame arrester where the hazard analysis wants one. Air moves through dampers and, on forced or balanced draft, through a fan, sometimes after a combustion air preheater that recovers stack heat, and the flue gas analyzer or oxygen trim closes the excess air loop. The process side reads its own instruments: temperature transmitters on pass outlets, tube skin thermocouples at the critical locations, a pressure transmitter on each pass, and flow measurement on the combined feed. Snuffing steam and quench connections, explosion relief per code and practice, a rupture disk or relief valve on the process coil where the closed sections can be blocked in, and winterization complete the picture. Buying the heater without its station is how startup arguments start.

Chapter 2 / 06

How Radiant and Convection Surfaces Share the Duty

The radiant section does most of the heat transfer from a small fraction of the surface. Flame temperatures are high, radiation scales with the fourth power of absolute temperature, and typical radiant average fluxes run 20 to 45 kilowatts per square meter by service, with lower values for coking sensitive fluids and higher for water and steam service. The design question is not whether the average fits but whether the peak fits: flame impingement or a burner directly under a tube row pushes local flux far above average, and local flux is what sets the inside film coking and the tube wall. Burner to tube geometry, firing rate distribution along the box, and the flame character of the chosen burners are therefore thermal design content, and a quotation that quotes only average flux is silent exactly where the risk lives.

Tube metal temperature is the number the whole machine protects. It is the outside wall temperature computed from the fluid film coefficient, the coke or fouling layer inside, the wall conduction, and the imposed flux, added to the fluid temperature; API 530 uses it to calculate thickness and remaining life against allowable stress for the material and time at temperature. The buyer sees it as two limits: the design tube metal temperature that sets metallurgy and thickness, and the operating tube skin indication from thermocouples attached to the hottest tubes. Every decision that adds resistance inside the tube, maldistributed flow among parallel passes, fouling, or runaways in flux, pushes skin temperature up, which is why pass flow balancing, stated minimum pass velocities, and tube skin instrumentation belong in the purchase specification and not in the commissioning apology.

The convection section earns the efficiency. Leaving the radiant chamber at 700 to 900 deg C, flue gas sweeps a bank of tubes, usually finned or studded to extend surface, transferring by convection at much lower flux per bare area but over a large extended area, and process preheat, steam generation, and superheat coils stack there by temperature level. The exit gas temperature from convection, commonly 300 to 450 deg C on moderate designs, decides the efficiency together with excess air, and the last of it is harvested by an economizer on a steam coil or by a combustion air preheater, pushing efficiency from the mid 80 percent band toward 90 to 92 percent and beyond with today's practice. Each efficiency point is fuel for twenty years, so the RFQ should price the convection and air preheat scope as an evaluated lifecycle line, not an optional extra.

Draft is the air and gas moving force, and the arrangement changes the hardware list. Natural draft heaters let stack buoyancy pull air through dampers and combustion gas through the setting, simple and self regulating in the old art, with capacity limited by stack height and air side resistance, which an air preheater's added drop consumes quickly. Forced draft pushes air with a fan at the burner front, allowing tight burner control and preheaters, at the cost of fan and control scope. Balanced draft runs a forced draft fan on the air side and an induced draft fan on the stack, holding the firebox slightly negative, which is the standard on larger modern units because it keeps flame gas out of the operator's face and allows deep air side hardware including preheaters and low NOx equipment. Each step up the draft ladder adds fans, dampers, controls, and failure modes to the purchase, and the RFQ should name the draft class explicitly rather than inherit it.

Emissions sit inside the thermal design, not beside it. Low NOx burners stage air or fuel to cool and slow the flame, flue gas recirculation does the same with mass, and both cost flame character and turndown range, which feeds back into radiant flux distribution. Selective catalytic reduction in the gas path, often in or after the convection bank where temperature fits the catalyst window, buys the last NOx points at catalyst and reagent cost, and carbon monoxide limits constrain how low excess air may go. The permit therefore belongs in the heater specification from the first sketch, because a heater designed to the wrong emissions basis cannot be tuned into compliance later; it can only be rebuilt.

Chapter 3 / 06

Heater Geometries, Draft, and Duty Boundaries

The cabin or box heater is the workhorse of refinery charge service: a rectangular radiant chamber with tubes on the walls and often a horizontal or sloped convection bank above, burners in the floor or on the walls, and pass arrangements that let each parallel flow path be balanced and isolated. Cabins suit duties from roughly 3 to over 100 megawatts, give good access to tubes and burners, and take every draft arrangement from natural to balanced. The cylindrical heater puts a vertical tube circle around a ring of floor burners in a round radiant chamber, with or without a convection section on top: it is compact, structurally simple, and economic in the 1 to 30 megawatt class, favored for hot oil, small reboiler, and gas processing duties. The vertical cylindrical with helical coil is a specialty of larger single stream duties and reforming service, where one continuous coil climbs the wall and the geometry suits high pressure single pass service.

Within each geometry the catalog divides by coil and service arrangement. Horizontal tube cabins suit heavy fluids that must not pocket in low points and services where drainage on shutdown matters; vertical tube cabins and cylindricals suit clean fluids and plots where ground area is precious. Multi pass arrangements with flow balancing orifices and, on critical service, individual pass temperature indication and pass valves, manage the parallel path problem; once through coils serve fluids that must not recirculate through the firebox, while recirculating designs trade that risk for lower flux per pass. Shield tubes at the radiant to convection interface, the shock bank, take the first and harshest convection duty and are usually bare rather than finned for exactly that reason. Tube supports, cast refractory or alloy hangers and guides, are consumables with their own temperature class, and the specification should treat them as such.

Hot oil and thermal fluid heaters deserve their own paragraph because they are quoted as a subclass: small to medium cylindrical or cabin heaters, often factory packaged, heating a thermal oil loop to 300 to 400 deg C for process users across a plant. The heater itself follows the same physics, but the purchase emphasizes the fluid vendor's film temperature limits, low flux to avoid cracking the oil, and packaged scope with expansion tank, pumps, and controls. The buyer of a hot oil heater should read this page for the heater core and the immersion heater and heat exchanger pages for the alternatives, and the selection chapter prices the fuel against electric heating honestly at small sizes. What the buyer must not do is specify a heater by fluid temperature alone, because it is the film and tube wall, not the bulk oil, that cracks.

Boundaries are worth stating bluntly. This page does not cover melting and heat treatment furnaces, which fire onto workpieces in the casting and thermal processing families, and it does not cover boilers or heat recovery steam generators, which make steam rather than heat a process fluid, though all share refractory, burner, and draft vocabulary. It is not the burner page: burners are components quoted inside this specification, and the industrial burner page is where the combustor itself is specified. It is not an electric heater: below roughly 200 to 250 deg C, steam and electric resistance equipment serve duties more cheaply and with less permitting, and the honest selection chapter sends small clean duties there. The geometry map below compresses the boundaries into one table.

Geometry and draftTypical duty classBest serviceWatch out for
Cabin box, balanced draft, convection and APH10 to 100 MWRefinery charge, vacuum, and large process dutyFan and BMS scope; peak flux at burner rows
Cabin box, natural draft3 to 30 MWSimpler plots, moderate efficiency targetsAir infiltration and stack capacity limits
Vertical cylindrical with convection1 to 30 MWHot oil, gas processing, small charge dutyLimited burner row geometry; access heights
Vertical cylindrical, radiant only0.5 to 10 MWCompact low first cost dutyExit gas temperature and efficiency floor
Helical coil vertical5 to 60 MWSingle stream high pressure and reforming serviceCoil replacement scope; pass isolation limits
Packaged hot oil heater0.5 to 8 MWThermal fluid loops to about 400 deg COil film temperature limits and low flux design
Chapter 4 / 06

Key Specification Parameters

The table below decodes the datasheet lines that decide whether a quoted heater matches the process and the permit. Each row is a purchase defining parameter; the paragraphs after the table explain what to demand and what a weak answer looks like.

AttributeTypical range or optionsWhat it decides
Absorbed duty0.5 to over 100 MWBox size, burner count, and the whole cost envelope
Process flow and outlet conditionFlow, inlet and outlet temperature and pressureCoil routing, pass count, and the thermal guarantee basis
Radiant average flux20 to 45 kW/m2 by serviceTube wall approach to coking and metallurgy limits
Design tube metal temperaturePer API 530 stress basisTube metallurgy, thickness, and remaining life margin
Tube metallurgy and scheduleCS, 1.25Cr, 2.25Cr, 9Cr, TP304 or 321, alloysCorrosion and creep envelope and coking tolerance
Draft arrangementNatural, forced, balancedFan and damper scope, air side hardware, infiltration
Efficiency basisExit gas temperature and excess air with or without APHTwenty year fuel cost and convection plus preheat scope
Emissions limitsNOx, CO, particulate by permitBurner selection, FGR or SCR scope, turndown envelope
TurndownCommonly 3:1 to 5:1 process, burner dependentOperating flexibility and flame stability at low fire
Burner managementNFPA style BMS, flame detector per burnerSafety scope, safety shutoff valves, purge and trip logic

The flux and tube metal rows carry the warranty. Demand the radiant flux distribution basis, not just the average: burner to tube geometry, firing distribution, and the peak to average ratio the design assumes, plus the calculated design tube metal temperature at the critical locations with the inside film basis stated. Ask what the design does when a pass runs dry or unbalanced: pass flow balancing hardware, minimum pass velocities, per pass temperature indication, and the trip philosophy on tube skin or pass differential. A quotation that cannot show peak flux handling is asking the buyer to accept the coking risk without the numbers, and the first decoking outage costs more than the difference between a good and a mediocre design.

The efficiency and emissions rows set the operating economics and the permit risk together. Efficiency should be quoted with its basis, exit gas temperature and excess air at design and at normal load, and with the air preheater scope separated so the buyer sees the fuel each option saves against its capital and fan cost. Emissions guarantees should be at the stack, at defined loads and fuels, with the burner technology named, low NOx staging, flue gas recirculation, or SCR, and with turndown limits inside which the guarantee holds, because a burner that only meets NOx between 70 and 100 percent load is a real constraint on a cycling plant. The second table compresses the metallurgy decision the way a specification meeting argues it.

Service and wall temperatureTube metallurgy to specifyCheck before order
Hot oil and light hydrocarbon, under 450 deg C wallCarbon steel or 1.25CrFouling allowance and minimum pass velocity
Heavy hydrocarbon, 450 to 600 deg C wall1.25Cr to 2.25Cr with thickness per API 530Peak flux basis, coking margin, tube skin points
Steam hydrocarbon and reforming service2.25Cr to 9Cr, TP321 where creep dictatesWeld practice and life basis at design wall
High temperature olefin and cracking serviceAustenitic and specialty alloysCarburization and nitriding basis, vendor references
Sulfur bearing fuel or sour serviceAlloy selection for the corrosion mechanismFuel analysis honesty and corrosion allowance

The mechanical rows close the specification. Refractory and casing design set heat loss and outer casing temperature, and the outdoor winter wind case belongs in the design conditions. Tube supports and hangers carry their own alloy class and creep life, shock bank and guide design follow the coil arrangement, and expansion of the coil, supports, and casing all belong in the designer's calculation book, which API 560 expects delivered. Stack height comes from dispersion modeling, and its interface with the draft class comes from the fan and damper study. The instrumentation list, pass outlet temperature transmitters, tube skin thermocouples, draft and pressure transmitter points, oxygen trim, and the BMS inputs, is part of the purchase, because those are the numbers the operating guarantee will be argued against.

Chapter 5 / 06

Selection Decision Factors and RFQ Language

The decision sequence is short enough to run as a specification meeting checklist, and each step eliminates a class of quotations before price comparisons begin.

  1. State the process duty honestly: flow, inlet and outlet conditions, fluid coking or cracking limits, allowable pressure drop, and the turndown the operations plan actually needs.
  2. Compute the temperature band: if steam or electric heating reaches the duty economically, stop, because fired heat carries flame risk and permitting that lower temperature sources do not.
  3. Choose geometry and draft from the chapter 3 table against duty size, plot, and efficiency target, and decide the air preheater scope on a fuel saving calculation, not on vendor enthusiasm.
  4. Fix the flux and metallurgy envelope: radiant average and peak flux basis, design tube metal temperature per API 530, tube materials, and the pass balancing and tube skin instrumentation that police them.
  5. Set the efficiency and emissions basis: exit gas temperature and excess air at named loads, permit limits at the stack, burner technology and SCR scope, and the turndown window the guarantees hold over.
  6. Define the safety package: BMS logic with flame detector per burner, safety shutoff valves and fuel trip philosophy, purge and lightoff sequence, snuffing and explosion relief, and the relief scope on blocked in coil sections.
  7. Fix interfaces: fuel gas conditioning, stack and dispersion, fans and dampers with their failure actions, structural and refractory design conditions including wind and seismic, and plot access for coil pulls.
  8. Fix the verification evidence: API 560 datasheet and calculation deliverables, performance test basis with tolerances, and inspection and material certificates.

Against neighboring equipment the comparison a specifier needs runs as follows, and it belongs here in the selection chapter rather than in the page title. Below roughly 200 to 250 deg C, a steam heated exchanger or an immersion heater serves the duty without a firebox, and the honest RFQ prices them first. Up to about 350 to 400 deg C, hot oil loops let one fired heater serve many users through an exchanger network, which is why packaged hot oil heaters are their own subclass here. Above those bands, or at large duty where fuel firing wins on cost, the fired heater is the machine. The burner inside it is specified on the industrial burner page, the melting and heat treatment furnaces belong to the casting families, the heat recovery steam generator makes steam from turbine exhaust, and the thermal oxidizer burns pollutants rather than heating product. Name the boundaries and every vendor quotes the same machine.

The RFQ block should be written once and reused. A complete block reads: process fluid and its coking or cracking limits, with the film or skin basis named; design, normal, and minimum flow with inlet and outlet temperature and pressure and allowable coil pressure drop; absorbed duty at design and normal; geometry and draft class named; radiant average and peak flux basis with design tube metal temperature and the API 530 thickness basis; tube specification including metallurgy, diameter, and schedule with supports and hangers classed; convection and air preheater scope with the efficiency calculation at stated loads and fuel; emissions limits at the stack with the burner technology and any SCR scope and the turndown window of the guarantee; burner count and duty with turndown and the BMS scope including flame detector per burner and safety shutoff valve arrangement; fuel analysis including sulfur and hydrogen content expectations; refractory and casing design conditions with winter and wind cases; stack height and dispersion basis; fans and dampers with failure actions; instrumentation list including tube skin thermocouples, pass outlet temperature transmitters, draft readings, and oxygen trim; snuffing, drainage, and explosion relief provisions; and the API 560 datasheet with calculation deliverables and the performance test method and tolerance. A quotation returned without the peak flux basis or the guarantee load window is incomplete at any price.

Chapter 6 / 06

Installation, Standards, Failure Modes, and Maintenance

Installation quality decides whether the guarantees survive the first fire. Refractory cureout follows the vendor bakeout curve with casing thermocouples watching, because trapped moisture spalls lining on first fire and showers the shock bank. The coil goes in with the supports and guides set for cold position so hot expansion finds its designed path, and pass orifices and valves are installed per the flow balance design, verified by measurement before first fire. Fuel gas systems prove their safety shutoff valves by leak test, burner lightoff follows the BMS sequence with purge volumes timed and each flame detector proven on extinction, and the draft system, dampers or fans, is proven through the full control range before process is introduced. Snuffing steam and quench connections are flushed and proven, because the one time they are needed is not the time to find a blocked line.

Commissioning proves the thermal and emissions case at measured loads. The performance test runs at design and normal duty with the API 560 method, reading outlet conditions, fuel consumption, excess air by the flue gas analyzer, exit gas temperature, and stack emissions against the guarantees, and tube skin thermocouples at the critical locations are recorded as the baseline for the campaign. Pass balance is verified at operating flow, and any pass running hot is rebalanced before acceptance, because the pass that leaves commissioning unbalanced is the one that cokes first. The BMS proves its trips by test: flame failure, low fire on lightoff, high tube skin or pass differential where configured, and fuel pressure excursions.

Failure modes in service follow a short and predictable list. Coke and fouling inside tubes raise skin temperature at constant duty, the signature being a slow climb in outlet temperature difference or tube skin at unchanged firing, and the remedies are flux discipline, pass balance, and on heavy service the online decoking or spalling procedures the process licensor defines. External tube corrosion and creep thinning track fuel sulfur and wall temperature, surveyed by thickness measurement at the defined locations each outage, with API 530 recalculating remaining life from the measured numbers. Refractory damage from rapid cycling opens heat leaks and hot casings, and tube supports and hangers creep and crack on their own schedule. Burner problems are the familiar set, plugged tips, unstable flame at turndown, and impingement after an air or fuel change, all of which the flame detector and the watchful eye of the outside operator catch first. Damper and fan faults on balanced draft units show as draft excursions and infiltration, and a heater running positive pressure leaks flue gas into the operator space, which is a safety finding, not an efficiency anecdote.

Maintenance intervals scale with service severity more than with calendar time. Clean light service runs annual outages with thickness survey on a sample basis and BMS proof testing per the code calendar. Heavy coking service plans decoking scope each turnaround and keeps pass balancing hardware and spare thermocouples in stock. Refractory and supports are inspected every outage against the baseline photos, and the calculation book delivered per API 560 is updated with the measured thickness and skin history, because that file is the remaining life argument and the next purchase specification's calibration. Instrument calibration follows the safety and process calendars, the tube skin and pass outlet temperature transmitters first among them, and every outage adds numbers to the file, which is how a purchasing file gets smarter instead of just older.

FAQ

What does API 560 actually require in a purchase specification?

It defines the datasheet and design content a petroleum fired heater purchase should carry: process and duty data, radiant and convection design basis, tube materials and supports, refractory and casing, draft and stack, instrumentation, burner management interfaces, and the inspection and testing regime. Writing the RFQ in API 560 vocabulary makes quotations comparable line by line and forces the vendor to state flux, efficiency, and emission bases explicitly rather than by brochure.

How much radiant flux is too much?

Service decides. Averages run roughly 20 to 45 kilowatts per square meter, with coking sensitive fluids at the low end and steam service at the high end, but the binding constraint is peak local flux and the tube metal temperature it produces, not the average. Demand the peak to average basis, the burner placement logic behind it, and the design tube metal temperature calculation, because coke forms where flux concentrates, not where the average lives.

Natural, forced, or balanced draft?

Natural draft is simplest and limited by stack pull, fine without air side hardware. Forced draft adds a fan and enables preheaters and tight burner control but runs the box positive. Balanced draft, forced plus induced fans, holds the firebox slightly negative, accepts air preheaters and SCR, and is the standard for large modern units, at the price of two fan systems and their failure modes. Name the class in the RFQ so fan, damper, and failure action scope is priced, not inherited.

When is a fired heater the wrong purchase?

Below roughly 200 to 250 deg C, steam or electric heating reaches the duty with less permitting and no flame risk, and up to 350 to 400 deg C a hot oil loop can carry one heater's output to many users. Fired heat earns its capital at high temperatures, large duties, or cheap fuel, and the honest selection chapter prices the alternatives before committing to a firebox.

How do I protect the tubes from coking?

Four levers, all bought at specification time: flux discipline with peak as well as average limits, pass flow balancing hardware with minimum pass velocities, tube skin thermocouples at the critical locations wired to alarms and trips where the service justifies, and decoking procedures planned before they are needed. A heater that leaves commissioning with unbalanced passes or dead skin points is carrying the coking risk the design was supposed to manage.

Does an air preheater make sense on every heater?

On large continuously fired heaters, almost always: recovering stack heat into combustion air buys several efficiency points and pays back quickly against fuel. On small or cycling heaters, the fan scope, added draft resistance, cold end corrosion on sulfur fuels, and capital may eat the savings, which is why the RFQ should price the air preheater as a lifecycle option with fuel saved per year stated at the plant's actual load profile.

What instrumentation is non negotiable?

Per burner flame supervision through a flame detector wired into the BMS with safety shutoff valves and purge logic, pass outlet temperature transmitters, tube skin thermocouples at the critical locations, draft indication at firebox and stack, and oxygen trim from the flue gas analyzer. Those are the numbers the safety case and the performance guarantee are both argued against, and they belong in the purchase scope, not in a later change order.

Sources

  1. BORN Inc., Heaters
  2. Sigma Thermal, Direct Fired Heaters