A computer room air handler (CRAH) moves air through a data hall and cools it with water supplied by a separate cooling plant. Fans return the conditioned air to equipment inlets through a raised floor, a duct, or a contained aisle. The unit may also filter, dehumidify, humidify or reheat the air as the design requires. Its purchasing boundary usually stops at the water, electrical, drainage, controls and air connections shown on the equipment drawing. The room must provide workable paths between those connections and the equipment the CRAH protects.
Specify the temperatures customers will measure at server inlets, the load the units must remove when a component is out, and the water the plant can deliver under that condition. A unit selected from a nominal kilowatt rating can fail any of those requirements. An air handler is only part of the heat path, so test the rack, room, unit and plant interfaces together before declaring the room available.
Use net sensible capacity at documented air and fluid conditions for thermal selection. Verify airflow separately against the pressure loss, leakage and air distribution of the installed hall. Award the unit on the combined duty points, service access and proven fault response.
Chapter 1 / 06
What a CRAH does in a computer room
A server fan pulls conditioned air through the electronic assemblies, raising its temperature before it leaves the rack. In a conventional front-to-back rack layout, the CRAH picks up this exhaust through a room or a dedicated hot-air path. It moves the warm return over tubes and fins carrying cold fluid, then sends the cooler air back to the rack inlets. The collector and discharge paths determine how much of the apparent unit capacity the racks actually receive. Hot exhaust that recirculates into an inlet can create a local temperature excursion while the average room sensor remains stable. Cold supply that reaches the return prematurely lowers entering air temperature and can reduce available coil duty.
The fan, coil, filter and valve form one equipment selection. A chiller may provide chilled water, while a dry cooler can serve an economizer circuit or other heat rejection duty where conditions allow. Some plants use a cooling tower and a separate condenser-water loop. A plate heat exchanger can isolate plant loops, with its approach temperature and pressure loss carried into the selection. A coolant distribution unit serves liquid-cooled IT and has its own fluid envelope. In a hybrid hall, list the heat allocated to each stream at each rack type and operating mode, including the air load that remains when cold plates cool only the largest chips.
A computer room air conditioner in the direct expansion sense delivers room air cooling using a refrigeration circuit with an evaporator and a compressor. Both types may have similar cabinets and room fan controls, so a front elevation cannot establish the heat-transfer arrangement. A building may also have an air-cooled condenser associated with refrigeration equipment elsewhere. Specify whether the room unit has a water coil, a refrigeration circuit or two separately defined cooling paths. Then identify what remains available when a field valve, plant branch, remote condenser or refrigeration component is isolated. Performance and maintenance responsibility depend on those supply boundaries.
Start with a room equipment inventory and an air-side load schedule. Include IT loads by rack population, internal power distribution losses within the cooled space, lighting, occupants and envelope or infiltration loads where material. Add air-side losses from liquid equipment if they occur in the hall. Use a coincident peak and a stated growth case, so each allowance shows its purpose. Building supply equipment, packaged fans and electrical auxiliaries may already appear in a vendor's net selection. Identify where that heat enters the air path before adding a separate fan heat allowance. A design with the same total demand at different rack coordinates can require a different number and arrangement of handlers.
Server inlets are often the best thermal compliance locations. Define height bands and the rack faces to instrument, and state which readings count during steady operation, a planned transition and a fault. A return grille sensor is valuable for coil control or diagnostics but will reflect a mixed air stream. An independent temperature transmitter at a rack inlet can help separate actual inlet behavior from a controller calibration problem. Establish the equipment and site thermal limits in the specification and attach the measurement method. The control target at the discharge, the equipment limit at the inlet and the normal operator display can all use different values.
A vendor may quote room units as a series with a range of capacities. Vertiv's Liebert CW literature describes a 26 to 181 kW chilled-water family with multiple fan and discharge arrangements [1]. STULZ lists a 22 to 260 kW family range for CyberAir 3PRO CW, with several downflow arrangements and an upflow option [2]. These are catalog ranges for the respective families. They do not establish net sensible duty for a particular unit until its configuration, air temperatures, chilled-water conditions and fan option are known. Compare selections at the same project conditions and preserve the vendor output sheets for commissioning.
Chapter 2 / 06
Types, placement and airflow paths
In a downflow arrangement, the unit draws return air near its upper section and discharges downward. A raised floor can act as a supply plenum with tiles feeding the racks, or a unit can discharge to a ducted distribution arrangement suited to the model. The usable plenum depth can be far smaller than the height on architectural drawings where cables, structural pedestals and pipe bridges interrupt the route. Locate obstructions, large penetrations and floor tile open areas on the coordination model. Specify the pressure and flow envelope at the handler and require the floor system designer to show delivery at the farthest or most obstructed positions.
In an upflow arrangement, the fan section sends air upward into a duct or open overhead distribution route, particularly where the installation uses a hard floor. The overhead duct can improve delivery to a distant row, but its fittings, branches, dampers and diffusers add resistance. A horizontal discharge or gallery arrangement places fans at the wall between the equipment service area and the room. This can fit a hall where an air path is built directly into the architecture. Include future gallery isolation and bypass openings in the evaluation. The physical air path matters more than the label on the product data sheet.
Containment changes the air-side problem. Cold-aisle containment restricts mixing around the rack inlets, and hot-aisle containment channels exhaust to the returns. Both require an accounting of doors, roof gaps, vacant rack spaces and cable openings. A blanking panel or sealing detail that disappears after an IT change alters the balance. If the room relies on differential pressure, place sensors where they read aisle pressure instead of a local jet. Furnish the nominal pressure reference and establish how airflow will be reset as servers turn their own fans up or down. A high supply pressure can increase bypass as well as move air to a remote inlet.
A centrifugal fan or plug fan can be selected by its operating point on the pressure-flow curve. An electronically commutated fan incorporates motor electronics. A cabinet can instead use a variable frequency drive with a separate AC motor. Confirm where speed is limited, which alarm is available for an individual fan, how minimum speed is handled and whether the fan data include the installed cabinet. A soft starter can shape the startup of some fixed-speed motor arrangements but provides no equivalent continuous fan-speed function. Avoid conflating the motor nameplate rating, the electrical branch requirement and the measured fan input at duty.
An array provides several fans with distributed flow across the coil. A stopped cell can become a recirculation path if there is no suitable isolation or backflow behavior. The remaining fans may need to run faster to maintain discharge pressure, which changes sound and motor heat. Ask whether degraded operation is one cell out, one drive out or an entire power section de-energized. A shared input disconnect, controller or supply can disable more cells than the fan count suggests. Use selection points for both intact and impaired operation, with the permitted residual airflow and electrical demand stated for each.
Arrangement
Air-path requirement
Drawing or test to request
Downflow to raised floor
Continuous plenum, sealed penetrations and a suitable tile pressure range
Floor plan with cable obstructions and measured tile flows at the far row
Upflow with duct
Available cabinet static after the specified external network
Supply duct layout and fan selections at clean and loaded filter points
Horizontal gallery discharge
Separation of supply and return with adequate open area
Gallery pressure map and personnel access plan in each fan state
Contained hot aisle
Return path sized for the exhaust volume at the declared rack load
Rack inlet map with doors shut and a specified door-open event
Multiple air zones
Row allocations that remain adequate as load distribution changes
Separate air and heat balances for each zone and failure mode
Chapter 3 / 06
Selecting sensible capacity, coil and water flow
Sensible heat changes the air temperature. Latent heat corresponds to moisture removed when condensation occurs. For a coil, total cooling is the sum under the specified conditions. A data hall normally has a high sensible share, but infiltration, outdoor air, pressurization, occupancy and humidity excursions can move the operating point. Ask the supplier to report net sensible duty, total duty, discharge dry-bulb temperature and a humidity result for each selection. Selection conditions should identify entering dry-bulb and moisture state together. A dry-bulb number alone leaves the latent component and condensation behavior undetermined.
On the air side, the steady sensible load relates to dry air mass flow, specific heat and temperature change. With a stated air density of 1.2 kg/m3 and a heat capacity of approximately 1.0 kJ/(kg K), an illustrative 60 kW sensible load with a 10 K air temperature rise implies about 5 m3/s through the load before allowances for bypass and mixing. This is a screening calculation rather than a fan or coil rating. Higher elevation and warmer air can change density, and leakage can raise the flow needed at the cabinet. The temperature difference across the coil is not automatically the same as the temperature rise through IT equipment.
On the water side, heat transfer is the fluid mass flow times its specific heat and temperature rise. An illustrative 60 kW water-side load at a 5 K rise requires about 2.9 kg/s for water near ordinary chilled-water conditions, using 4.18 kJ/(kg K). Treat this example as a heat balance for a declared total water-side load. It omits corrections for glycol and any change due to latent cooling or fan heat already included in the selected duty. Specify the concentration, fluid properties, entering fluid temperature, allowable return range and available pressure at the equipment. Request a coil curve for actual fluid, which may have more resistance and less heat capacity than plain water.
A coil selection is a coupled result. Additional rows or closer fin spacing can improve heat exchange at a given set of inlet temperatures, with costs in pressure loss, serviceability and fan power. Raising the chilled-water supply temperature may enlarge the economizer window at the plant but also reduce the temperature difference driving cooling. The room equipment must retain useful sensible duty at that warmer condition. Ask suppliers to identify whether the selection is dry or wet and to give air-side and water-side drops for the nominal and worst credible points. For a variable water-temperature plant, obtain several states across the intended scheduling range.
Pressure available for the coil branch must include other installed losses. A centrifugal pump or split-case pump feeds the headers, and an expansion tank supports pressure management in a closed loop. Allocate branch pressure to strainers, connectors, the heat exchanger and the control valve. A Y strainer or basket strainer needs a service location and an allowance for pressure loss as debris collects. In systems with a make-up connection, the backflow preventer belongs to the water-supply protection design. It should not be treated as a generic accessory to every coil branch.
A two-way control valve can reduce branch flow as load falls. The plant must still manage its distribution pressure and any minimum flow requirement. Ask the system designer to check valve authority and rangeability at low duty as well as at the fully open point. Unstable flow during a cold morning or after an IT load step can make air temperature drift even when the selected unit is large enough. Include a way to measure branch flow, coil inlet and outlet temperatures and suitable pressure points. Those readings establish whether a unit shortfall originates in the coil, the air path or the plant.
Selection input
Required output
Reason
Entering dry bulb and moisture state
Total and net sensible capacities with discharge conditions
Makes latent removal and sensible capacity visible
Water temperature and fluid concentration
Flow, return temperature and coil pressure drop
Supports the pump and plant heat balance
Airflow at specified external static
Unit speed, fan input and residual capacity with a failed fan
Shows the usable operating point
Part-load points
Valve position or range, fan speed, humidity behavior
Reveals unstable or inefficient low-load operation
Warm-water or fault point
Remaining duty under the declared one-out case
Tests cooling availability when the plant is constrained
Chapter 4 / 06
Key specifications and evidence at tender
A schedule should describe the cabinet as it will be shipped, with filters, fan arrangement, coil circuit, control valve and any humidifier or reheat section identified. Quoting a base unit and adding options after selection can change internal pressure loss, operation at low fan speed, package weight and the electrical schedule. Keep the configuration code beside the thermal selection. Require revisions of both when the cabinet changes. The acceptable delivered performance starts at the cabinet boundary, while coordination drawings explain how it will reach the racks.
Schedule line
What to write
Verification artifact
Sensible capacity
Net kW at defined air and fluid conditions
Selection printout showing fan setup and all input conditions
External static
Pa at flow with measurement stations named
Fan curve and field airflow test plan at cabinet boundary
Filter classification, seal arrangement and clean or final resistance
Filter cut sheet plus alarm setpoint with replacement resistance
Coil pressure rating
Working pressure, connection size and materials for the actual fluid
Coil submittal, pressure-test record and piping connection sketch
Supply power
Voltage, frequency, current, feeds and essential circuit allocation
Wiring diagram and restart or alternate feed evidence
Controls
List of alarms, command permissions and trend points
Controls sequence, points schedule and network integration test
Noise
Sound power by band and operating state where required
Test surface or rated data with fan speed and conditions
Service access
Filter, motor, valve and coil clearance including extraction route
Dimensioned access envelope and removal instructions
The external static requirement should state which resistances are inside the supplier's selection and which the system designer adds. Filter resistance, coil pressure drop and housing losses are often internal. The duct or room pressure route outside the casing is a system input. A loaded filter test point can be represented with a manufacturer selection or agreed physical method. Ensure the two are consistent. A free-air fan number can look high while providing no evidence of performance at the project's resistance. Ask for the sound measurement basis on the actual selected configuration, including higher operating speeds during loss of a unit or fan.
Electrical schedules need the entire cabinet load and what starts after utility recovery. A room distribution cabinet or upstream motor control center may feed auxiliaries or plant pumps on a different schedule. Assign protection and the circuit breaker coordination to the electrical design. A diesel generator can provide alternate building power, while an industrial UPS is sometimes reserved for distinct loads or controls. List the equipment actually on each power train. A fan restarted on standby power may still have no chilled water or a controls network at the time it starts.
Sensible capacity, flow and electrical input all need a measurement reference. Specify whether fan heat is already subtracted from an advertised net value and where airflow stations are located. Identify whether the scheduled sound quantity is room sound pressure or source sound power, and at what position or operating point it will be evaluated. Give the room temperature, duct and overpressure assumptions used for test tolerances. The contract should identify what a supplier must achieve at the unit and what the integrator must achieve in the assembled room, especially when test temperature or water conditions differ from design.
Mechanical fit involves more than cabinet width. Include floor-loading approval, rigging route, fan removal, coil withdrawal, supports, valve and actuator removal access, drip protection and drain slope. An underfloor pipe located in the same bay as fan removal can make future changeout impossible. If a leak detector depends on gravity routing, map credible paths around raised floor supports and cable conduits. A vendor's cabinet drawing rarely shows nearby structural or piping conflicts. Ask for a coordination review before freezing connections and provide a replacement path that remains clear after a future row expansion.
Chapter 5 / 06
Humidity, filtration, teaming and maintenance
Moisture removal happens when the effective coil surface is below the incoming air dew point. A sensible-only duty may be satisfied with warmer water and a dry coil in normal weather, while humid air entering from a vestibule can drive wet operation. Conversely, an aggressive cold coil can condense more moisture than a room strategy calls for, leading to humidification and cooling at the same time. Specify allowed room dew point and any humidity limits at a particular temperature, and coordinate with the outdoor air or building humidity design. Add a drain system and overflow detection for all credible wet operating conditions.
Some applications use a humidity management function within the CRAH. Define whether humidification is integral or handled separately, whether reheat is available, and which unit can enable each mode. A temperature controller may act locally while a supervisory controller resets a common target. Specify allowable deadbands and sensor accuracy at the intended room conditions. A humidity sensor located in cold discharge air cannot be interpreted the same way as one in warm return air without the corresponding temperature. A front-panel percentage therefore requires context before it is used to make cooling or moisture decisions.
The filter protects the coil and other surfaces from particulate loading. Selection should consider filter frame sealing, access pressure loss, availability of replacements and the owner's particulate limits. A loaded filter can reduce airflow even when motor speed reaches the upper limit, and a bypass gap can leave pressure drop looking low. An air quality monitor may help investigate room episodes if its sensing capability matches the issue. It is distinct from the unit's filter differential pressure switch or transmitter. Specify a clean baseline and confirm how the building team will receive a high differential pressure alarm.
Team control must define authority. Local firmware should have an agreed response when a supervisor or network becomes unavailable. For example, the contract can specify which local setpoint remains active, whether fans continue, what the valve does after loss of a critical sensor and how alarms clear. A building PLC can coordinate pump or valve interfaces, and an HMI panel can display state, without moving responsibility for embedded CRAH protections to the facility integrator. Put source, destination, sampling rate, scaling and acknowledgement behavior beside each important point.
Avoid having several controllers pursue incompatible airflow and temperature targets. If every unit independently treats the same nearby aisle as under-supplied, parallel fans can hunt while another aisle remains warm. A shared controller must also be robust to loss of the sensor it uses for reset. Assign control to zones where appropriate and distinguish air-side speed from water-side capacity. Test the system as IT fans step up, a floor tile is changed and an upstream temperature changes. Trends synchronized across the selected measurements reveal whether an excursion coincides with a fan response, valve movement or a loss of plant supply.
Maintenance cases should be part of the installed design. Define whether a fan can be isolated independently, how controller faults are reported, and the service isolation boundary for water. Specify filters by verifiable dimensions and performance, not simply a cabinet trade name. Require access to drain traps, sensor pockets, valve strainers, electrical panels and water connections. Maintain a baseline with airflow, fan speed, water flow, approach temperatures and pressure drop taken at a repeatable state. A gradual drift in several signals helps distinguish a fouled coil from a clogged filter or a failed valve actuator.
Chapter 6 / 06
Selection, RFQ and integrated acceptance
An N+1 statement is meaningful only after the failed item and load have been defined. Determine the number of units needed at maximum declared air-side load and site conditions, then evaluate loss of one CRAH and credible common supply failures. A common header, switchboard, leaking valve station or controller may remove a larger group than the equipment schedule suggests. Identify the rooms and racks affected by each isolation boundary. Verify that the remaining units can deliver air to the affected rows without relying on an open containment door or heat migrating slowly between zones.
Establish project states before inviting bids: initial occupancy, design population, credible unequal rack loading and maximum agreed future load. Provide both normal water temperatures and the warmest permitted supply at design load. Give each bidder the same duct resistance, floor assumptions and data hall humidity state. Request net sensible duty at the specified points, total useful duty under degraded operation and fan input by operating speed. Define what stays powered during generator transfer and whether any thermal ride-through is required. Require the proposed equipment to be tied to a dated schedule and arrangement drawing so substitutions can be evaluated on the same basis.
A factory test can establish controls, alarms, rotation status and some mechanical performance of the actual build. Discuss what thermal rig conditions are available and how measured results map to the project. On site, verify room pressure and flow with final containment and racks or representative simulators installed. Compare independent reference sensors with the control points, trend the room during steady operation, then use agreed failure and recovery scenarios. Record starting load, water temperatures, initial fan state and any excluded spaces so the test can be repeated. Treat corrected temperature data and raw readings as separate entries in the commissioning record.
Acceptance case
Record
Evaluate
Normal peak sensible load
Room inlet map, discharge air, branch temperatures, flow and fan input
Cooling meets room limits and design water balance
One declared unit unavailable
Initial load and inlet temperatures through the transition
Worst rack recovers within the contract envelope
Plant supply temperature increase
Duty, valve travel, fan response and condensate state
No unplanned loss of required sensible capacity
Control network interrupted
Local setpoint, command permissions and alarm restoration
Unit preserves the agreed local fallback
Water or electrical isolation for maintenance
Affected zone and remaining available equipment
Documented service work can proceed under the declared duty
Define what each party owns if a test fails. A unit vendor should support diagnosis of cabinet capacity, valve commands and fan data. Mechanical and electrical designers must provide actual plant conditions and branch availability. Room and ICT teams may be responsible for cabinets, containment, blanking and load distribution. Confirm contract allowances for test load, independent sensors, overnight monitoring and correction of the sequence. A single capacity shortfall can have several contributors. With named measurement points and an interface schedule, each can be investigated without replacing a working cabinet unnecessarily.
Select the thermal measurement intervals to match the response being tested. A long historian average can hide the warmest few seconds after a stop, while a single noisy sensor sample can misidentify the section of row with persistent trouble. Keep the raw readings and use the acceptance statistic prescribed by the owner. Verify sensor time alignment across air, branch water and power data before running the test. On a row with mixed air and liquid cooling, separate failures of the direct fluid path and the room air supply can have different thermal time constants. Agreed test profiles should define when a sequence ends and when the room is considered stable again.
For additions to an existing hall, field measurements can replace assumptions in the bid package. Trend valve lift and suction conditions available to the plant pump before increasing the branch flow. Confirm air distribution with neighboring units in their current configuration. Corridor or ceiling space needed for a new top discharge may already be occupied, and an existing water branch may serve equipment that is not obvious in the current controls display. Identify temporary provisions for keeping occupied racks within their operating envelope during equipment replacement. Specify whether new operation depends on balancing, sealing or controller upgrades outside the air-handler order.
In the purchase order, give the latest load map, airflow and pressure inputs, fluid conditions, dimensions and responsibility matrix precedence over preliminary catalog selections. Require a deviation register from the supplier and record the recovery actions available when a promised option is missing. Specify the spares and the controls documentation an operator needs after warranty, including how to distinguish a remote enable problem from a local fault. Close the procurement with signed records for the unit checks, integrated room checks and remaining punch items. Preserve the selection files used for approval so future growth and replacement projects have a usable reference.
FAQ
What is the difference between a CRAH and a CRAC?
A CRAH usually cools data hall air with a water or glycol coil supplied from a separate plant. A direct expansion CRAC uses a refrigerant circuit for room cooling. Both can look similar and both can support precision control. Confirm which cooling circuit, outdoor equipment and power dependences appear on the actual project drawing.
Should I specify total cooling or sensible cooling?
Schedule both, with net sensible capacity as a key criterion for the IT and other sensible load. Total cooling includes latent removal when moisture condenses. Entering temperature and moisture, actual water conditions, airflow and fan heat accounting determine how much of the selected duty is usable. Keep the comparable selection output from each bidder.
How do I choose downflow, upflow or gallery discharge?
Trace the complete route from the cabinet to critical rack inlets and then back to the return. A downflow cabinet can serve a raised plenum, an upflow cabinet can serve overhead distribution and a horizontal unit can suit a gallery. Confirm the built pressure losses and available service path before fixing the style.
Can water temperature be increased to save plant energy?
A warmer plant setpoint can improve heat rejection or economizer availability in some designs. It also reduces the coil driving temperature difference and changes condensation behavior. Request unit selections at the warmest intended supply temperature and test the integrated response at the corresponding load. Review upstream water limits and downstream rack inlet compliance together.
Does a CRAH have to dehumidify?
That depends on the room moisture balance and facility humidity strategy. The coil removes moisture when its surface is sufficiently cold, but the hall may have separate equipment for ventilation or humidity. Define acceptable dew point, where moisture is controlled and how wet operation or overflow is detected. Coordinate humidification and dehumidification so they do not work against each other.
How should fan redundancy be verified?
Identify the component to be lost and the residual performance required at load. Losing one fan, a shared drive or an entire feed creates different cases. Demand the surviving airflow at the specified static, and check for backflow through inactive sections. Verify that the available fans serve the critical rack locations under the agreed case.
What should the CRAH request for quotation include?
Provide the rack and room load cases, entering air and chilled-water conditions, airflow and static requirements, room arrangement and exact failure cases. Include the fan and water control strategy, power details, sound limit and service clearances. Ask for vendor selections, connection drawings, commissioning points and an explicit list of deviations from the schedule.